Fort St James building permit fees
How much does a building permit cost in Fort St James?
In Fort St James a building permit costs 0.6% of the construction value ($6 per $1,000), with a $50 minimum, under Schedule A of the Building Bylaw. A manufactured home is $150 for a single wide and $300 for a double wide. The fee is paid before the permit is issued.
Key facts
| Lowest fee | $50 (minimum building permit fee).Building Bylaw No. 932, 2014, Schedule A Building Permit Fees (PDF, office consolidation November 13, 2024), Schedule A (k) · Wording matched the official text retrieved 2026-11-08Official wordingMinimum Building Permit Fee $50.00 |
|---|---|
| How the fee is worked out | Residential (dwellings, garages, carports, patios) and commercial, industrial or institutional work: 0.6% of construction value ($6 per $1,000). Same rate for moving or demolishing a building and for minor alterations, additions and repairs. Manufactured home: $150 single wide, $300 double wide.Building Bylaw No. 932, 2014, Schedule A Building Permit Fees (PDF, office consolidation November 13, 2024), Schedule A (a) to (h) · Wording matched the official text retrieved 2026-11-08Official wording0.6% of construction value ($6.00 per $1,000.00) Manufactured Home (Single Wide) $150.00 Manufactured Home (Double Wide) $300.00 |
| Application or plan review fee | None set. The Building Bylaw has no separate application or plan review fee.Read: Building Bylaw No. 932, 2014, Schedule A Building Permit Fees (PDF, office consolidation November 13, 2024) |
| Other fees | Wood-burning appliance and chimney (new installations): $100. Change of occupancy: $100 plus 0.6% of construction value. Cancelling the note against land title: $200. Work started without a permit after a Stop Work Notice: extra 25% of the fee (50% if outstanding 30 days). Security may be required for damage to public property; no amount set.Building Bylaw No. 932, 2014, Schedule A Building Permit Fees (PDF, office consolidation November 13, 2024), Schedule A (e), (i), (j); s. 20.3, 20.4 · Wording matched the official text retrieved 2026-11-08Official wordingWood Burning Appliance and Chimney $100.00 Change of Occupancy $200.00 pay an additional charge equal to 25% of the pay an additional charge equal to 50% of the When required, the building official may require security for the repair or replacement of |
| How to pay | The District calculates the fee once it receives the application and supporting documents, and the fee must be paid before the permit is issued. The pages read do not say how to pay.Building Bylaw No. 932, 2014, Schedule A Building Permit Fees (PDF, office consolidation November 13, 2024), s. 8.1.3; Building Permit Application (fillable PDF), Page 3, footer · Wording matched the official text retrieved 2026-11-08Official wordingthe applicant for a building permit has paid the building permit fee as prescribed in PERMIT FEE WILL BE CALCULATED UPON RECEIPT OF THIS APPLICATION AND SUPPORTING DOCUMENTS, |
| Bylaw | Building Bylaw No. 932, 2014, Schedule “A” Building Permit FeesBuilding Bylaw No. 932, 2014, Schedule A Building Permit Fees (PDF, office consolidation November 13, 2024) · Wording matched the official text retrieved 2026-11-08Official wordingSCHEDULE “A” BUILDING PERMIT FEES |
How it works
The fees come from Schedule A of the District's Building Bylaw No. 932. The District calculates your fee once it receives the application and supporting documents, and the fee must be paid before the permit is issued. The building official may set the construction value using the District's "Formula for Estimated Value of Construction Policy", which was not found on the website.
Fees
- Minimum fee: $50.
- Residential (dwellings, garages, carports, patios) and commercial, industrial or institutional work: 0.6% of construction value ($6 per $1,000).
- Moving or demolishing a building, and minor alterations, additions and repairs: the same rate.
- Manufactured home: $150 single wide, $300 double wide.
- Wood-burning appliance and chimney (new installations): $100.
- Change of occupancy: $100 plus 0.6% of construction value.
- Cancelling the note against land title: $200.
- Work started without a permit after a Stop Work Notice: an extra 25% of the fee (50% if outstanding 30 days).
Good to know
- The bylaw has no separate application or plan review fee.
- If a permit is returned within six months without work starting, 75% of the fee is refunded.
- Security may be required for damage to public property; the bylaw sets no amount.
- The pages read do not say how to pay. Call the District office (250-996-8233).
- A 2026 amending bylaw to the District's fees could not be read, so confirm the current fees with the District.
What you'll need
- Completed Building Permit Application form and supporting documents, so the District can calculate the fee
Official forms and pages
The same question in other places
Vanderhoof · Fraser Lake · Prince George · Mackenzie · Granisle · Houston
Sources
- Building Bylaw No. 932, 2014, Schedule A Building Permit Fees (PDF, office consolidation November 13, 2024) (read 2026-11-08)
- Building Permit Application (fillable PDF), District of Fort St James (read 2026-11-08)
- Contact Us, District of Fort St James (read 2026-11-08)