Short answer

In Logan Lake you need a building permit for most construction, alteration, repair, demolition, plumbing work and retaining walls over 1.2 m. Applications go through Thompson-Nicola Regional District staff, who run the District's building inspections. TNRD says complete applications take 3 to 5 weeks.

Key facts

Needed forA permit is required whenever work regulated by the Building Regulations Bylaw is done: construction, alteration, repair, demolition or moving of buildings, change of use or occupancy, fireplaces and chimneys, plumbing installation or alteration, and retaining walls over 1.2 m (4 ft).Building Regulations Bylaw No. 602, 2006 (PDF, consolidated to May 16, 2023), s. 6.1; s. 1.3.1; Building Permits, Thompson-Nicola Regional District, Building Permit FAQ: What type of work requires a permit? · Wording matched the official text retrieved 2026-11-08
Official wording
A permit is required whenever work regulated by this bylaw is to
greater than 1.2 m (4 ft) in height
the work involved in the demolition when the whole or any part of a building is demolished or removed
all parts of the building when the whole or any part of a building is moved
all parts of the building affected by the change of use when occupancy
Construct a new home
Construct an addition to an existing building or manufactured home
Move a building
Not needed forNot covered by the bylaw: single-storey accessory buildings under 20 m² (215 ft²); farm buildings of low human occupancy under 600 m² on land used for bona fide agriculture; unroofed decks at or under 600 mm (24 in) above ground beside a one- or two-family home; fences, paving and retaining structures under 1.2 m (4 ft).Sources differ: The TNRD application guide says accessory buildings under 10 m² (107 sq ft) in municipalities need no permit, and the TNRD page lists 'Construct a sundeck' without a height limit. The District's own bylaw (20 m²; decks 600 mm or lower exempt) is followed here. Bylaw 602 s. 1.3.2.1 also exempts buildings exempted by Division A, Part 1 of the Building Code.Building Regulations Bylaw No. 602, 2006 (PDF, consolidated to May 16, 2023), s. 1.3.2; s. 2.21; Building permit application guide for dwellings (PDF, Feb 2024), p. 3, Building permit application exemptions · Wording matched the official text retrieved 2026-11-08
Official wording
Single-storey accessory buildings less than 20 m2 (215 ft2) in building area;
Low-Human Occupancy farm buildings less than 600 m2
Unroofed decks attached to or adjacent to single and two-family dwellings if the deck surface is 600 mm (24 in) or less above the adjacent ground level.
but specifically excludes landscaping, fences, paving and retaining structures less than 1.2 m (4 ft) in height.
10 square metres (107 sq. ft.) in municipalities;
How to applyBuilding inspection services for the District are run by Thompson-Nicola Regional District (TNRD) staff. Application forms are available at the Municipal Office, #1 Opal Drive, or can be downloaded from the TNRD site. TNRD accepts complete applications only.Planning & Development, Planning & Development, Building Inspections; Building Permits, Thompson-Nicola Regional District, Building Permits page · Wording matched the official text retrieved 2026-11-08
Official wording
The District of Logan Lake Building Inspection Services are facilitated by staff from the Thompson-Nicola Regional District (TNRD).
Building Permit Application forms are available at the Municipal Office at #1 Opal Drive, Logan Lake, BC or you may visit the TNRD Site below and download a form.
Only complete applications will be accepted for processing.
To obtain a TNRD building permit, please contact the TNRD at 250-377-8673.
What to submitTNRD requires a title copy dated within 30 days and a copy of all registered covenants. Its guide adds a site plan, floor plans and other construction drawings. The Building Official may also require surveys, engineering and registered-professional letters of assurance.Building Permits, Thompson-Nicola Regional District, Building Permits page (effective April 1, 2026); Building permit application guide for dwellings (PDF, Feb 2024), pp. 5-7; Building Regulations Bylaw No. 602, 2006 (PDF, consolidated to May 16, 2023), s. 6.3 and 6.5 · Wording matched the official text retrieved 2026-11-08
Official wording
A copy of the current property title, dated within 30 days of the application date; and
A copy of all registered covenants associated with the property.
Site Plan to include the following:
Floor Plans include the following:
The Building Official may require a registered professional to
Processing timeTNRD says it is committed to a 3 to 5 week processing time for complete applications, depending on seasonal levels of construction and development.Building Permits, Thompson-Nicola Regional District, Building Permit FAQ: How long does it take to obtain a permit? · Wording matched the official text retrieved 2026-11-08
Official wording
We are committed to a 3 to 5 week processing time period for complete applications, dependent on seasonal levels of construction and development.
InspectionsInspections in Logan Lake are scheduled for Thursdays. Book by calling the TNRD Inspection Request Line at 250-377-7076 or through tnrd.ca. The TNRD guide says to book by 12 p.m. the business day before and quote the permit number; the bylaw requires at least one working day's notice.Planning & Development, Planning & Development, Building Inspections; Building permit application guide for dwellings (PDF, Feb 2024), p. 15; Building Regulations Bylaw No. 602, 2006 (PDF, consolidated to May 16, 2023), s. 15.4 · Wording matched the official text retrieved 2026-11-08
Official wording
Inspections in Logan Lake are scheduled for Thursdays.
To book an inspection you may call the Inspection Request Line at 250-377-7076 or visit the TNRD Site at www.tnrd.ca.
no later than 12pm on the business day prior to the scheduled inspection day.
working day's notice to the District of Logan Lake
ContactBuilding Inspector: 250-319-8112 or 250-377-8673 ext. 2252. TNRD Building Inspection Services: building@tnrd.ca, 250-377-8673. District Municipal Office: 250-523-6225.Planning & Development, Planning & Development, Building Inspections; Building Permits, Thompson-Nicola Regional District, Building Permits page; Applications, Forms, Permits · Wording matched the official text retrieved 2026-11-08
Official wording
A Building Inspector is available for inquiries at 250-319-8112 or 250-377-8673 ext. 2252.
For queries about building permits, contact the TNRD at building@tnrd.ca or 250-377-8673
PO Box 190, #1 Opal Drive Logan Lake, B.C., VOK 1W0 Canada Phone: 250.523.6225 After-Hours Emergency: 250.523.6274 Fax: 250-523-6678
BylawDistrict of Logan Lake Building Regulations Bylaw No. 602, 2006 (consolidated to May 16, 2023).Building Regulations Bylaw No. 602, 2006 (PDF, consolidated to May 16, 2023), s. 1; Planning & Development · Wording matched the official text retrieved 2026-11-08
Official wording
District of Logan Lake Building Regulations
District of Logan Lake Building Regulations Bylaw 602

How it works

The District of Logan Lake's Building Regulations Bylaw No. 602 requires a permit for construction, alteration, repair, demolition or moving of buildings, a change of use or occupancy, fireplaces and chimneys, plumbing installation or alteration, and retaining walls over 1.2 m (4 ft). Building inspection services for the District are run by Thompson-Nicola Regional District (TNRD) staff, and TNRD lists the same kinds of work.

Not covered by the bylaw: a single-storey accessory building under 20 m² (215 ft²), a farm building of low human occupancy under 600 m² on land used for bona fide agriculture, an unroofed deck 600 mm (24 in) or less above ground beside a one- or two-family home, and fences, paving and retaining structures under 1.2 m.

Steps

  1. Get the application form at the Municipal Office, #1 Opal Drive, or download it from the TNRD site. TNRD accepts complete applications only.
  2. Include a title copy dated within 30 days and a copy of all registered covenants. TNRD's guide adds a site plan, floor plans and other drawings, and the Building Official may ask for surveys, engineering or professional letters of assurance.
  3. TNRD calls you when the permit is ready to pick up and pay for.
  4. Book inspections on the TNRD Inspection Request Line, 250-377-7076, or through tnrd.ca. Inspections in Logan Lake are on Thursdays.

Good to know

  • TNRD's guide says to book by 12 p.m. the business day before and quote your permit number; the bylaw requires at least one working day's notice.
  • A registered owner or the owner's agent may apply.
  • Zoning limits on size, height and setbacks still apply; see the zoning-lookup answer.
  • TNRD's guide gives a smaller exemption for accessory buildings (under 10 m²) than the District's bylaw (20 m²). Confirm with the Building Inspector before you build.

Official forms and pages

The same question in other places

Ashcroft · Cache Creek · Lytton · Lillooet · Merritt · Kamloops

Building permits in British Columbia: how to apply, by municipality →

Sources

  1. Building Regulations Bylaw No. 602, 2006 (PDF, consolidated to May 16, 2023), District of Logan Lake (read 2026-11-08)
  2. Building Permits, Thompson-Nicola Regional District (read 2026-11-08)
  3. Building permit application guide for dwellings (PDF, Feb 2024), District of Logan Lake (read 2026-11-08)
  4. Planning & Development, District of Logan Lake (read 2026-11-08)
  5. Applications, Forms, Permits, District of Logan Lake (read 2026-11-08)

Checked by script, not yet by a person: the official wording behind 8 of 8 facts was matched to the official text. How answers are checked.