Short answer

In New Hazelton the building permit fee is set in the Fees and Charges Bylaw as the cost of the project x 0.005%, as the schedule is written. No minimum fee or separate application fee is listed. Because the rate looks unusual, confirm the amount with the District Office.

Key facts

Lowest feeNone set. The Fees and Charges Bylaw schedule lists no minimum fee.
How the fee is worked outResidential and commercial: cost of the project x 0.005%, as written in the schedule. The value of construction is the contract price plus a reasonable allowance for extras, or the Building Inspector's estimate where there is no contract price.Fees and Charges Bylaw No. 393, 2026, Schedule A, Development: Building Permits and Inspections · Wording matched the official text retrieved 2026-11-08
Official wording
Cost of project x
0.005%
shall be the contract price together with a reasonable
allowance for extras or, where there is no contract price, the approximate cost of
Application or plan review feeNone set. The Fees and Charges Bylaw schedule lists no separate application fee.
Other feesDemolition permit: $75 (single family or two-unit dwelling) or $100 (other building). Move a building in, out or within the District: $75. Lapsed permit renewal $75. Permit extension $75. Temporary building $250. Permit fees are not refundable.Fees and Charges Bylaw No. 393, 2026, Schedule A, Development: Building Permits and Inspections · Wording matched the official text retrieved 2026-11-08
Official wording
Permit – Other Building
Permit to move, remove or place a building within or into the District
Permit renewal: Lapsed Permit
Temporary Building $250.00
Cancellation of a Permit – The fees paid above are not refundable under any condition.
How to payNot confirmed. The fee schedule does not say how or when permit fees are paid.
BylawFees and Charges Bylaw No. 393, 2026, Schedule A (Development: Building Permits and Inspections)Fees and Charges Bylaw No. 393, 2026, Bylaw 393, s. 1; Schedule A · Wording matched the official text retrieved 2026-11-08
Official wording
BYLAW NO. 393, 2026
Council hereby establishes the fees and charges as set out in Schedule “A” to this bylaw.
BUILDING PERMITS AND INSPECTIONS

How it works

The Fees and Charges Bylaw No. 393, 2026, Schedule A (Building Permits and Inspections), sets the fee for residential and commercial building permits as the cost of the project x 0.005%, as written in the schedule. The value of construction is the contract price plus a reasonable allowance for extras, or the Building Inspector's estimate where there is no contract price. We could not tell from the text whether the 0.005% figure is exact, so confirm it with the District Office before you budget.

The schedule lists no minimum fee and no separate application or plan review fee. It does not say how or when permit fees are paid.

Steps

  1. Call the District Office at 250-842-6571 or email info@newhazelton.ca to confirm the fee for your project.
  2. Ask how and when to pay.

Good to know

Other fees in Schedule A:

  • Demolition permit: $75 for a single family or two-unit dwelling, $100 for any other building.
  • Moving a building in, out or within the District: $75.
  • Lapsed permit renewal: $75. Permit extension: $75.
  • Temporary building: $250.
  • Permit fees are not refundable.
  • A development permit ($400) and a development variance permit ($750) are separate permits.

Official forms and pages

The same question in other places

Hazelton · Smithers · Telkwa · Granisle · Terrace · Houston

Building permit fees in British Columbia, by municipality →

Sources

  1. Fees and Charges Bylaw No. 393, 2026 (PDF) (read 2026-11-08)
  2. Bylaws, District of New Hazelton (read 2026-11-08)
  3. District of New Hazelton home page (read 2026-11-08)

Checked by script, not yet by a person: the official wording behind 3 of 6 facts was matched to the official text; 2 are recorded as not set; 1 could not be confirmed. How answers are checked.