# Sayward building permits: when you need one and how to apply

**Question:** Do I need a building permit in Sayward, and how do I apply?

**Short answer:** In the Village of Sayward you need a building permit for any construction, addition, alteration, change of use or demolition of a building or structure. Buildings under 10 m² are generally exempt. Get the application package from the Village's Building Permits page, or call the Village Office.

**Who handles it:** Municipal (Village of Sayward, https://www.sayward.ca)  
**Cost:** A plan processing fee plus a permit fee, set in the Fees and Charges Bylaw. See the building-permit-fees answer.  
**How long:** The Village's page and Building Bylaw do not state a processing time. An application is cancelled if it is not complete within 180 days.  
**Where:**
- In person: Village Office, 652 H'Kusam Way, Sayward, BC (Monday to Friday, 9:00 a.m. to 4:00 p.m. (closed holidays))
- Phone: Village Office, 250-282-5512 (The Building Permits page names no contact; call the Village Office.)

## Key facts

- **Needed for:** Any construction, addition, alteration, change of use or demolition of a building or structure in the Village.
  - Source: [Building Permits, Building Permits page](https://www.sayward.ca/business-development/building-permits)
  - Official wording: "A building permit is required for any construction, addition, alteration, change of use or demolition of a building or structure located within the boundaries of the Village of Sayward."
  - Check: wording matched the official text retrieved 2026-11-08
- **Not needed for:** Buildings or structures exempted by Part 1 of the Building Code, including those under 10 m² (107.6 sq ft) in building area (with some exceptions), and fences and retaining structures under 2 m (6.6 ft) in height.
  - Source: [Building Bylaw No. 334, 2005 (PDF, consolidated), s. 5.2](https://www.sayward.ca/sites/1/files/2021-05/Bylaw%20334%20-%20Building%20Bylaw%20Consolidated%20Version%2C%20for%20convenience%20only.pdf)
  - Official wording: "buildings or structures exempted by Part 1 of the Building Code, including buildings or" … "fences and retaining structures less than 2 metres (6.6 feet) in height."
  - Check: wording matched the official text retrieved 2026-11-08
- **How to apply:** Complete the Building Permit Application package posted on the Village page. An owner can authorize a contractor to apply by completing an Agent Authorization Form.
  - Source: [Building Permits, Building Permits page](https://www.sayward.ca/business-development/building-permits)
  - Official wording: "you can authorize your contractor to apply for a permit for you by completing an Agent Authorization Form" … "Building Permit Application package"
  - Check: wording matched the official text retrieved 2026-11-08
- **What to submit:** Signed application form and owner's acknowledgment; land title search made within 14 days; a site plan by a BC Land Surveyor; floor plans; cross sections; elevations; copies of health or safety approvals (such as sewage disposal permits); letters of assurance.
  - Source: [Building Bylaw No. 334, 2005 (PDF, consolidated), s. 9.1](https://www.sayward.ca/sites/1/files/2021-05/Bylaw%20334%20-%20Building%20Bylaw%20Consolidated%20Version%2C%20for%20convenience%20only.pdf)
  - Official wording: "a copy of a land title search made within 14 days of the date of the application" … "a site plan, prepared by a British Columbia Land Surveyor showing:" … "floor plans showing the dimensions and uses of all areas"
  - Check: wording matched the official text retrieved 2026-11-08
- **Processing time:** Not confirmed. The published pages do not say how long a permit takes.
- **Inspections:** Not confirmed. The Village's page and the bylaw do not say how to book an inspection.
- **Contact:** Village Office, 250-282-5512.
  - Source: [Staff Directory, Staff directory](https://www.sayward.ca/contact/staff-directory)
  - Official wording: "Chief Administrative Officer (250) 282-5512"
  - Check: wording matched the official text retrieved 2026-11-08
- **Bylaw:** Village of Sayward Building Bylaw No. 334, 2005 (Consolidated)
  - Source: [Building Bylaw No. 334, 2005 (PDF, consolidated), Title](https://www.sayward.ca/sites/1/files/2021-05/Bylaw%20334%20-%20Building%20Bylaw%20Consolidated%20Version%2C%20for%20convenience%20only.pdf)
  - Official wording: "BYLAW NO. 334 Village of Sayward Building Bylaw, 2005"
  - Check: wording matched the official text retrieved 2026-11-08

## How it works

The Village of Sayward reviews plans against the BC Building Code, the Village's [Building Bylaw No. 334](https://www.sayward.ca/sites/1/files/2021-05/Bylaw%20334%20-%20Building%20Bylaw%20Consolidated%20Version%2C%20for%20convenience%20only.pdf) and other regulations. The owner is responsible for the permit. You can authorize a contractor to apply by completing an Agent Authorization Form, but you must still make sure the contractor has the permit before work starts. The bylaw also requires a moving permit to relocate a building.

The bylaw does not apply to buildings or structures exempted by Part 1 of the Building Code, including those under 10 m² (107.6 sq ft) in building area (with some exceptions), and fences and retaining structures under 2 m (6.6 ft) high. Failing to get a permit can mean costly delays, legal action or removal of completed work.

## Steps

1. Call the Village Office at 250-282-5512 to confirm that your project needs a permit.
2. Download the Building Permit Application package from the Village's Building Permits page.
3. Gather the documents listed in the package and the bylaw. The Chief Administrative Officer may waive some items.
4. Submit the application. The page does not say whether this is in person, by email or by mail, so ask the Village Office.
5. Pay the plan processing fee with the application, and the permit fee before the permit is issued.

## Good to know

- The Building Permits page has an Inspections heading with no text, and the bylaw does not say how to book an inspection. Ask the Village Office.
- Water and sewer connection fees are due when the permit is issued.

## What you'll need

- Signed application form and owner's acknowledgment
- Land title search made within 14 days
- Site plan by a BC Land Surveyor, floor plans, cross sections and elevations
- Copies of health or safety approvals, such as sewage disposal permits
- Letters of assurance
- Agent Authorization Form, if a contractor applies for you

## Official forms and pages

- [Building Permit Application package (PDF)](https://www.sayward.ca/sites/1/files/2021-06/0%20Building%20Permit%20Application%20-%20Complete%20Set%202021.pdf)
- [Building Permits, Village of Sayward](https://www.sayward.ca/business-development/building-permits)
- [Building Bylaw No. 334 (PDF)](https://www.sayward.ca/sites/1/files/2021-05/Bylaw%20334%20-%20Building%20Bylaw%20Consolidated%20Version%2C%20for%20convenience%20only.pdf)

## Related questions

- [Sayward building permit fees](https://govhandbook.com/ca/bc/sayward/building-permit-fees.md)
- [Sayward permits for decks, sheds, carports and garages](https://govhandbook.com/ca/bc/sayward/deck-shed-garage-permit.md)
- [Sayward fence rules: permits and height limits](https://govhandbook.com/ca/bc/sayward/fence-rules.md)
- [Sayward secondary suite and carriage house rules](https://govhandbook.com/ca/bc/sayward/secondary-suite.md)
- [Sayward zoning: find your zone and what it allows](https://govhandbook.com/ca/bc/sayward/zoning-lookup.md)

## The same question elsewhere

- [Building permits in British Columbia: how to apply, by municipality](https://govhandbook.com/ca/bc/building-permit.md)
- [Campbell River](https://govhandbook.com/ca/bc/campbell-river/building-permit.md)
- [Gold River](https://govhandbook.com/ca/bc/gold-river/building-permit.md)
- [Tahsis](https://govhandbook.com/ca/bc/tahsis/building-permit.md)
- [Alert Bay](https://govhandbook.com/ca/bc/alert-bay/building-permit.md)
- [Port McNeill](https://govhandbook.com/ca/bc/port-mcneill/building-permit.md)
- [Courtenay](https://govhandbook.com/ca/bc/courtenay/building-permit.md)

## Sources

- [Building Permits, Village of Sayward](https://www.sayward.ca/business-development/building-permits) (read 2026-11-08)
- [Building Bylaw No. 334, 2005 (PDF, consolidated)](https://www.sayward.ca/sites/1/files/2021-05/Bylaw%20334%20-%20Building%20Bylaw%20Consolidated%20Version%2C%20for%20convenience%20only.pdf) (read 2026-11-08)
- [Staff Directory, Village of Sayward](https://www.sayward.ca/contact/staff-directory) (read 2026-11-08)

_Checked by script, not yet by a person: the official wording behind 6 of 8 facts was matched to the official text; 2 could not be confirmed. Gov Handbook is an independent guide, not affiliated with Village of Sayward. How answers are checked: https://govhandbook.com/methods/ · Canonical page: https://govhandbook.com/ca/bc/sayward/building-permit/_