Short answer

In Slocan the building permit fee comes from the Regional District of Central Kootenay (RDCK) fee schedule: $100 for work valued up to $1,000, then $10.50 per $1,000 or portion for $1,000 and over. A non-refundable plan-check deposit of $50 to $200 is paid with the application.

Key facts

Lowest fee$100 base fee for construction valued from $1 to $1,000.RDCK Building Bylaw No. 2200, Schedule A, Permit Fees, Schedule A, A. Building Permit Fees · Wording matched the official text retrieved 2026-11-08
Official wording
repair of any building and the placement of single or double-wide manufactured homes. BASE FEE: $ 1.00 - $1,000.00 $100.00 $1,000.00 and over $10.50 per $1000.00 or a portion
How the fee is worked outConstruction value $1 to $1,000: $100. For $1,000 and over: $10.50 per $1,000 or portion (the schedule's wording). Fee is reduced 10% for municipal permits where the municipality provides inspection administrative service. Residential value may use per-sq-ft rates (detached garage $30).RDCK Building Bylaw No. 2200, Schedule A, Permit Fees · Wording matched the official text retrieved 2026-11-08
Official wording
$10.50 per $1000.00 or a portion
Detached garage
Sundeck
Accessory Building up to 550 sq. ft.
$1,000.00 and over $10.50 per $1000.00 or a portion
The calculated fee shall be reduced by 10% for Municipal Permits where the municipality
Application or plan review feePlan-check deposit with the application: $100 single-family dwelling, $200 multi-family/industrial/commercial/institutional, $50 accessory building or addition. Non-refundable and credited against the permit fee.RDCK Building Bylaw No. 2200, Schedule A, Permit Fees, Schedule A, E. Plan Check Deposit; RDCK Building Bylaw No. 2200, 2010 (PDF, consolidated for convenience), s. 12.2 · Wording matched the official text retrieved 2026-11-08
Official wording
PLAN CHECK DEPOSIT
Single-family dwelling
Accessory Building or Addition
which is non-refundable and must be credited against the building permit fee
Other feesPlumbing $10.50 per fixture; demolition $150; moving a building $200; temporary building $200; pools (fence requirements) $100; re-inspection $150; permit renewal $100; commercial change of occupancy $200; manufactured home set-up $350.RDCK Building Bylaw No. 2200, Schedule A, Permit Fees, Schedule A, B and C · Wording matched the official text retrieved 2026-11-08
Official wording
Plumbing System
Demolition
Re-Inspection
Permit Renewal
Moving a building.
Pools (fence requirements) $100.00
Manufactured home set up single wide or double wide $350.00
How to payThe permit fee must be paid in full before the permit is issued.RDCK Building Bylaw No. 2200, 2010 (PDF, consolidated for convenience), s. 12.1 · Wording matched the official text retrieved 2026-11-08
Official wording
must be paid in full prior to issuance of any permit under this Bylaw
BylawRDCK Building Bylaw No. 2200, 2010, Schedule A (Permit Fees), the schedule the Village's Building Permits page links to.RDCK Building Bylaw No. 2200, Schedule A, Permit Fees; Building Permits, Building Permits page · Wording matched the official text retrieved 2026-11-08
Official wording
SCHEDULE'A' - PERMIT FEES
BUILDING BYLAW NO. 2200, 2010
For current building permit fees refer to the schedule here

How it works

Slocan uses the RDCK building permit fees in Schedule A of RDCK Building Bylaw No. 2200. The fee depends on the value of the construction. The permit fee must be paid in full before the permit is issued (bylaw); the payment method is not stated.

Steps

  1. Work out the construction value. Some residential work may use per-square-foot rates (a detached garage is $30), which apply where higher than the contract cost.
  2. Pay the plan-check deposit with your application.
  3. Pay the permit fee in full before the permit is issued.

Good to know

  • Permit fee: $100 for construction valued from $1 to $1,000; $10.50 per $1,000 or portion (the schedule's wording) for $1,000 and over.
  • The schedule reduces the calculated fee by 10% for municipal permits where the municipality provides the inspection administrative service. Ask the Village Office whether that applies in Slocan.
  • Plan-check deposit: $100 single-family dwelling, $200 multi-family, industrial, commercial or institutional, $50 accessory building or addition. It is non-refundable and credited against the permit fee.
  • Other fees: plumbing $10.50 per fixture; demolition $150; moving a building $200; temporary building $200; pools (fence requirements) $100; re-inspection $150; permit renewal $100; commercial change of occupancy $200; manufactured home set-up $350.
  • If work starts without a permit and a Stop Work notice stays outstanding for 30 days, the bylaw adds a 25% extra fee.

Official forms and pages

The same question in other places

Silverton · New Denver · Nelson · Kaslo · Castlegar · Nakusp

Building permit fees in British Columbia, by municipality →

Sources

  1. RDCK Building Bylaw No. 2200, Schedule A, Permit Fees (PDF) (read 2026-11-08)
  2. RDCK Building Bylaw No. 2200, 2010 (PDF, consolidated for convenience) (read 2026-11-08)
  3. Building Permits, Village of Slocan (read 2026-11-08)

Checked by script, not yet by a person: the official wording behind 6 of 6 facts was matched to the official text. How answers are checked.