How much does a building permit cost?

Coquitlam, British ColumbiaChecked against official textSources read 2026-11-05

Short answer

In Coquitlam, a building permit fee is a base amount plus a rate per $1,000 of estimated construction value, set in Schedule D of the Fees and Charges Bylaw. A separate application fee of $106.70 or 50% of the issuance fee is due first, and $679.70 for a new house. Confirm with the City.

Key facts

Lowest feeFor work valued $0 to $5,000 (no registered professional), $35.60 per $1,000 of estimated construction value, with no base fee. With a registered professional, $34.10 per $1,000.Fees and Charges Bylaw No. 5484, 2025, Schedule D (PDF, consolidated with Bylaw No. 5551, 2026), Schedule D, Tables 1 and 2 · Wording matched the official text retrieved 2026-11-06
Official wording
Table 1. Building Permit Fee (without Registered Professional)
$0 to $5,000 - $ 35.60
$0 to $5,000 - $ 34.10
How the fee is worked outFee is a base amount plus a rate per $1,000 of estimated construction value. Table 1 (no registered professional): to $5,000 $35.60; $5,001-20,000 $46.40 + $26.70; $20,001-50,000 $178 + $20.40; $50,001-500,000 $510.70 + $13.70; over $500,000 $1,150 + $12.40. Table 2 (registered professional) is slightly lower.Fees and Charges Bylaw No. 5484, 2025, Schedule D (PDF, consolidated with Bylaw No. 5551, 2026), Schedule D, Table 1 · Wording matched the official text retrieved 2026-11-06
Official wording
Value of Construction Fees Fee per $1,000
$5,001 to 20,000 $ 46.40 $ 26.70
$20,001 to $50,000 $ 178.00 $ 20.40
$50,001 to $500,000 $ 510.70 $ 13.70
$500,001 and greater $ 1,150.00 $ 12.40
Table 2. Building Permit Fee (with Registered Professional)
Application or plan review feeApplication intake fee, paid on invoice before plan review: $106.70 or 50% of the issuance fee (the schedule's wording is unclear), and $679.70 for a new single or two family dwelling. The remaining permit fee is paid before the permit is issued. An older City guide says 25%.Sources differ: The City's Accessory Detached Buildings Guide (June 2021) says 25% of the permit value is due when applying, with the balance at issuance. The bylaw schedule is followed. Whether the intake fee is credited against the permit fee is implied by the 'outstanding balance' wording only.Fees and Charges Bylaw No. 5484, 2025, Schedule D (PDF, consolidated with Bylaw No. 5551, 2026), Schedule D, Document & Services; Permit Application Review, Step 4 and Step 6; Building Projects - Homeowner/Residential, Apply for a Permit · Wording matched the official text retrieved 2026-11-06
Official wording
Building Permit or 50% of the issuance fee for the building permit for which the application is $ 106.70
Building Permit (new Single/Two family dwelling) $ 679.70
Refer to the Fees and Charges Bylaw Schedule "D" (PDF) for application intake fees.
Pick up plans after plan review has been satisfactorily completed and pay the permit fee outstanding balance.
Other feesPlumbing $79 minimum (two fixtures), $36.40 per extra fixture. Demolition $119.60 accessory, $337.90 other. Re-inspection $108.40 minimum plus $128.90 per extra hour. Six-month extension $306.60. Security deposit (Building Bylaw Sch. A): nil under $50,000; $2,500 for $50,000+ house additions or accessory buildings; $1,500 pool or retaining wall; $1,000 demolition.Fees and Charges Bylaw No. 5484, 2025, Schedule D (PDF, consolidated with Bylaw No. 5551, 2026); Building Bylaw No. 3598 (PDF, consolidated September 2026), Schedule A, Security · Wording matched the official text retrieved 2026-11-06
Official wording
The minimum plumbing system permit fee is $79.00 This fee includes two fixtures.
Fixtures roughed in (Note 1) - fee each fixture $ 36.40
Accessory Building $ 119.60
All Other $ 337.90
Re-inspection Fees
Each additional hour or part thereof $ 128.90
Plan recheck Fee (changes or addition subject to a recheck) $ 245.00
Building Permit Extension (6 months extension) $ 306.60
Swimming Pool or Retaining Wall $1,500.00
Demolition permit $1,000.00
Additions, alterations & accessory $2,500.00
How to payFor online applications, staff email an invoice with payment instructions for the intake fee; the permit is issued after the remaining fee is paid. Only plumbing permits and alternative solution applications can be paid online; other building permits are paid at City Hall, or by cheque.Permit Application Review, Steps 4 and 6; Building & Construction, Building Permit Applications · Wording matched the official text retrieved 2026-11-06
Official wording
City staff will contact the applicant by email with an attached invoice and instructions for payment which will include the permit number(s).
Currently for plumbing permits and alternative solution applications we are able to process application payments online.
For all other building permit applications you will be asked to provide payment at City Hall.
Cheques can be mailed to City Hall or placed in the drop box
BylawFees and Charges Bylaw No. 5484, 2025, Schedule D (Building Bylaw Fees & Charges), consolidated with Bylaw No. 5551, 2026; fees are charged under the Building Bylaw No. 3598, 2003Fees and Charges Bylaw No. 5484, 2025, Schedule D (PDF, consolidated with Bylaw No. 5551, 2026) · Wording matched the official text retrieved 2026-11-06
Official wording
BYLAW NO. 5484, 2025
Building Bylaw Fees & Charges
Consolidated with amendments in Bylaw: (1) 5551, 2026

How it works

Fees are set in Schedule D of the City of Coquitlam's Fees and Charges Bylaw 5484 and charged under the Building Bylaw 3598. The permit fee uses Table 1 if no registered professional is involved, and Table 2 if one is. Each band lists a base amount and a rate per $1,000 of estimated construction value. The schedule does not say whether the rate applies to the whole value or only the part above the band's lower limit, so ask Building Permits before working out a total. Retaining walls use Table 3.

Fee bands

  • Table 1 (no registered professional): up to $5,000, $35.60 per $1,000 with no base fee; $5,001 to $20,000, $46.40 plus $26.70 per $1,000; $20,001 to $50,000, $178 plus $20.40; $50,001 to $500,000, $510.70 plus $13.70; over $500,000, $1,150 plus $12.40.
  • Table 2 (registered professional): up to $5,000, $34.10 per $1,000; $5,001 to $20,000, $43.30 plus $25.60; $20,001 to $50,000, $170.30 plus $19.40; $50,001 to $500,000, $485.90 plus $13.20; over $500,000, $1,175 plus $11.80.

Good to know

  • Application (intake) fee, invoiced before plan review: $106.70 or 50% of the issuance fee (the schedule's wording is unclear), and $679.70 for a new single or two-family dwelling. The remaining fee is paid before the permit is issued. An older City guide says 25%, so confirm the amount with the City.
  • Other fees: plumbing $79 minimum (two fixtures) plus $36.40 per extra fixture; demolition $119.60 for an accessory building, $216.10 for an in-ground pool, $337.90 otherwise; re-inspection $108.40 minimum plus $128.90 per extra hour; six-month extension $306.60.
  • Security deposit (Building Bylaw Schedule A): none under $50,000; $2,500 for house additions or accessory buildings of $50,000 or more; $1,500 for a pool or retaining wall; $1,000 for demolition.
  • Online applications are invoiced by email. Only plumbing permits and alternative solution applications can be paid online; other building permits are paid at City Hall or by cheque. Most City fees add a 2% charge on credit cards.

Official forms and pages

The same question in other places

Port Coquitlam · Port Moody · Belcarra · Anmore · New Westminster · Burnaby

Building permit fees in British Columbia, by municipality →

Sources

  1. Fees and Charges Bylaw No. 5484, 2025, Schedule D (PDF, consolidated with Bylaw No. 5551, 2026), City of Coquitlam (read 2026-11-05)
  2. Building Bylaw No. 3598 (PDF, consolidated September 2026), City of Coquitlam (read 2026-11-05)
  3. Permit Application Review, City of Coquitlam (read 2026-11-05)
  4. Building & Construction, City of Coquitlam (read 2026-11-05)
  5. Building Projects - Homeowner/Residential, City of Coquitlam (read 2026-11-05)

Checked by script, not yet by a person: the official wording behind 6 of 6 facts was matched to the official text. How answers are checked.