How much does a building permit cost in Anmore?

Anmore, British ColumbiaChecked against official textSources read 2026-11-08

Short answer

In Anmore a building permit costs $21 per $1,000 of construction value up to $5,000 (minimum $75), with lower rates on higher values. You first pay a non-refundable $500 application fee, which is deducted from the permit fee if the permit is approved.

Key facts

Lowest feeConstruction up to $5,000: $21 per $1,000, with a $75 minimum. A non-refundable $500 building permit application fee (including plumbing) is paid first; if the permit is approved it is deducted from the permit fee.Fees and Charges Bylaw No. 608-2019, Schedule A (PDF, consolidated to November 21, 2025), Schedule A, Building Permits · Wording matched the official text retrieved 2026-11-08
Official wording
Construction up to $5,000.00 $21.00 per $1,000 (min $75.00)
Building Permit Application Fee including Plumbing $500.00
If permit is approved the application fee is deducted from permit fees
How the fee is worked outBased on construction value: up to $5,000: $21 per $1,000 (min $75); $5,001 to $20,000: $15 per $1,000 plus $75; $20,001 to $100,000: $11 per $1,000 plus $600; $100,001 to $500,000: $8 per $1,000 plus $1,350; over $500,000: $7 per $1,000 plus $2,500. The Building Official sets the value; an owner may use a quantity surveyor's value instead.Fees and Charges Bylaw No. 608-2019, Schedule A (PDF, consolidated to November 21, 2025), Schedule A, Permit Fees; Building Bylaw No. 583-2018, s. 15.2 · Wording matched the official text retrieved 2026-11-08
Official wording
Construction from $5,001.00 to $20,000.00 $15.00 per $1,000 + base fee of
Construction from $20,001.00 to $100,000.00 $11.00 per $1,000 + base fee of
Construction from $100,001.00 to $500,000.00 $8.00 per $1,000 + base fee of
Construction from $500,001.00 and over $7.00 per $1,000 + base fee of
Building permit fees are calculated based on the building value determined by the
Application or plan review feeBuilding permit application fee (including plumbing) $500; plumbing permit application only $75. Both are non-refundable. If the permit is approved, the application fee is deducted from the permit fees. The plan-processing part of the fee is forfeited if the permit cannot be issued within 180 days.Fees and Charges Bylaw No. 608-2019, Schedule A (PDF, consolidated to November 21, 2025), Schedule A, Application Fees; Building Bylaw No. 583-2018, s. 12.4 · Wording matched the official text retrieved 2026-11-08
Official wording
Building Permit Application Fee including Plumbing $500.00
Plumbing Permit Application Fee only $75.00
If permit is approved the application fee is deducted from permit fees
permit fee forfeited when the permit cannot be issued within 180 days of the date of
Other feesDemolition: $100 up to 56 m², $350 over 56 m². Plumbing fixtures $20 each (minimum $75). Fireplaces and solid fuel appliances $360 each. Re-inspection after the second inspection $120. Construction before a permit: double the permit fee. Security deposit refundable at occupancy: $5,000 for work under $100,000, $10,000 otherwise.Fees and Charges Bylaw No. 608-2019, Schedule A (PDF, consolidated to November 21, 2025) · Wording matched the official text retrieved 2026-11-08
Official wording
Permit Fee for a demolition of a building or structure 56m2 $100.00
Plumbing fixtures $20.00 per fixture (min. $75.00)
Construction prior to issuance of a building permit Double the permit fees
Re-Inspection Fee after second consecutive inspection (3rd $120.00
For Building Permits less than $100,000.00 value of $5,000.00
How to payPay the application fee in Cloudpermit before review starts. After approval you get an invoice for the permit fees, including the refundable security deposit. Pay in person at the Community Hub front desk (cheque, cash or debit), by cheque (mail or Hub mail slot), or by Visa or Mastercard through OptionPay (third-party fees apply, only after an invoice number is issued).Cloudpermit, How to Apply · Wording matched the official text retrieved 2026-11-08
Official wording
Once approved, you’ll receive an invoice for the permit fees, which includes the refundable security deposit amount.
In-person at the Anmore Community Hub front desk by cheque, cash, or debit.
VISA or Mastercard through the online payment service OptionPay.
BylawAnmore Fees and Charges Bylaw No. 608-2019, Schedule A (Inspection Services Department: Building Permits including Plumbing), consolidated to Amendment Bylaw No. 723-2025; Anmore Building Bylaw No. 583-2018, Part 15Fees and Charges Bylaw No. 608-2019, Schedule A (PDF, consolidated to November 21, 2025), cover; Building Bylaw No. 583-2018, s. 15.1 · Wording matched the official text retrieved 2026-11-08
Official wording
Anmore Fees and Charges Bylaw Amendment Bylaw No. 723-2025
Permit and field review fees, deposits, security and liability insurance coverage

How it works

The Village of Anmore charges building permit fees under Schedule A of its Fees and Charges Bylaw No. 608-2019 and Part 15 of the Building Bylaw No. 583-2018. The fee is based on the value of the construction. The Building Official sets the value, but an owner may use a quantity surveyor's value instead.

Construction value Fee
Up to $5,000 $21 per $1,000 (minimum $75)
$5,001 to $20,000 $15 per $1,000 plus $75
$20,001 to $100,000 $11 per $1,000 plus $600
$100,001 to $500,000 $8 per $1,000 plus $1,350
Over $500,000 $7 per $1,000 plus $2,500

Steps

  1. Pay the non-refundable application fee in Cloudpermit before the review starts: $500 for a building permit (including plumbing), or $75 for a plumbing permit on its own.
  2. If the permit is approved, the application fee is deducted from the permit fees.
  3. After approval you receive an invoice for the permit fees, including the refundable security deposit.
  4. Pay in person at the Community Hub front desk (cheque, cash or debit), by cheque (mail or the Hub mail slot), or by Visa or Mastercard through OptionPay. Third-party fees apply to OptionPay, and it can be used only after an invoice number is issued.

Good to know

  • The plan-processing part of the application fee is forfeited if the permit cannot be issued within 180 days.
  • Demolition is $100 up to 56 m² and $350 over 56 m². Plumbing fixtures are $20 each (minimum $75). Fireplaces and solid fuel appliances are $360 each. A re-inspection after the second inspection is $120.
  • Starting construction before you have a permit doubles the permit fee.
  • The security deposit, refunded at occupancy, is $5,000 for work under $100,000 and $10,000 otherwise.

Official forms and pages

The same question in other places

Port Moody · Belcarra · Coquitlam · Port Coquitlam · New Westminster · District of North Vancouver

Building permit fees in British Columbia, by municipality →

Sources

  1. Fees and Charges Bylaw No. 608-2019, Schedule A (PDF, consolidated to November 21, 2025), Village of Anmore (read 2026-11-08)
  2. Building Bylaw No. 583-2018 (PDF), Village of Anmore (read 2026-11-08)
  3. Cloudpermit, Village of Anmore (read 2026-11-08)

Checked by script, not yet by a person: the official wording behind 6 of 6 facts was matched to the official text. How answers are checked.