GovHandbook

Courtenay building permit fees

How much does a building permit cost?

Courtenay, British ColumbiaChecked against official textSources read 2026-11-05

Short answer

A City of Courtenay building permit costs $150 plus 1% of the value of construction. A non-refundable application fee of $150, or 25% of the permit fee if that is higher, is credited to the permit fee when the permit is issued. Other charges may apply.

Key facts

Lowest fee$150 plus 1% of the value of construction (building permit). A demolition permit is $150.Building Bylaw No. 3114, Appendix A (consolidated October 2025, PDF), Appendix A, Permit Fees · Wording matched the official text retrieved 2026-11-06
Official wording
All $150 + 1% of the value of construction
Demolition Permits All $150
How the fee is worked outBuilding permit: $150 plus 1% of the value of construction, for all buildings. Fire suppression system permits: $75 (simple) or $125 (complex) plus 1% of construction value.Building Bylaw No. 3114, Appendix A (consolidated October 2025, PDF), Appendix A, Permit Fees · Wording matched the official text retrieved 2026-11-06
Official wording
All $150 + 1% of the value of construction
Complex Buildings and structures $125 + 1% of the value of construction
Simple buildings $75 + 1% of the value of construction
Application or plan review feeNon-refundable application fee: $150 or 25% of the building permit fee, whichever is highest. It is credited against the permit fee when the permit is issued, and forfeited if the application expires (not issued within 180 days).Building Bylaw No. 3114, Appendix A (consolidated October 2025, PDF), Appendix A; ss. 10.9, 10.22 · Wording matched the official text retrieved 2026-11-06
Official wording
$150 or 25% of the building permit fee
prescribed below whichever is the highest
be credited against the permit fee when the permit is issued;
the building permit has not been issued within 180 days from the date an application is received under this Part
Other feesDemolition permit $150. Plumbing permit: $75 + $10 per fixture (simple) or $125 + $15 (complex). Re-inspection $125 (Inspections page says $100). Security deposit $3,000 for single or two-family dwellings. Fee doubled (max $10,000) if work starts before the permit.Sources differ: Re-inspection: bylaw Appendix A says $125 (s. 10.47: second and each later re-inspection); the Inspections page says $100 if more than two inspections are needed. Bylaw followed. Other Appendix A items: inspection fees, archive research, copies of plans $10 per sheet, design modification $85/hour. Multi-residential, commercial, industrial and institutional security deposit: $3,000 minimum or $300 per metre of frontage to a maximum of $15,000.Building Bylaw No. 3114, Appendix A (consolidated October 2025, PDF), Appendix A; s. 10.21; Inspections, Re-inspections · Wording matched the official text retrieved 2026-11-06
Official wording
Simple buildings and structures $75 + $10 for each fixture
Complex buildings and structures $125 + $15 for each fixture
Re-inspection $125
Security Deposit for Single/two family $3000
The building permit or other permit fee is doubled for every permit application if construction commenced before the building official issued a permit, to a maximum of $10,000.00.
Demolition Permits All $150
A $100 re-inspection fee applies if more than two inspections are required due to incomplete or non-compliant work.
How to payThe application fee is paid with the online application. Permit fees and other costs are calculated by City staff and are due when the permit is issued.Building and plumbing permits, Geodetic elevations on site plans; Building Bylaw No. 3114, Appendix A (consolidated October 2025, PDF), ss. 10.2(a), 10.10 · Wording matched the official text retrieved 2026-11-06
Official wording
Permit fees and other associated costs will be calculated by staff and are due upon permit issuance.
be made in the form prescribed by the building official and signed by the owner
Before receiving a building permit for a building or structure, the owner must first pay to the City:
BylawBuilding Bylaw No. 3114, Appendix A (Fees and Charges)Building Bylaw No. 3114, Appendix A (consolidated October 2025, PDF) · Wording matched the official text retrieved 2026-11-06
Official wording
Appendix A – Fees and Charges
Non-Refundable Application Fees

How it works

Fees are set in Appendix A of Building Bylaw No. 3114. The application fee is paid with the online application. City staff calculate the permit fee and other costs, and they are due when the permit is issued.

Fees

  • Application fee (non-refundable): $150 or 25% of the building permit fee, whichever is highest. It is credited against the permit fee when the permit is issued, and forfeited if the application expires (no permit issued within 180 days).
  • Building permit: $150 plus 1% of the value of construction, for all buildings.
  • Demolition permit: $150.
  • Plumbing permit: $75 + $10 per fixture (simple buildings) or $125 + $15 (complex).
  • Fire suppression system permit: $75 (simple) or $125 (complex), plus 1% of construction value.
  • Security deposit: $3,000 for single or two-family dwellings.

Good to know

  • Re-inspection is $125 under the bylaw. The City's Inspections page says $100 if more than two inspections are needed; confirm with Building.
  • If work starts before the permit is issued, the permit fee is doubled, to a maximum of $10,000.
  • The bylaw also sets extension, transfer, plan-copy and other fees; see Appendix A.
  • The City's pages do not say how building permit fees can be paid.

Official forms and pages

The same question in other places

Comox · Cumberland · Powell River · Campbell River · Port Alberni · Qualicum Beach

Building permit fees in British Columbia, by municipality →

Sources

  1. Building Bylaw No. 3114, Appendix A (consolidated October 2025, PDF), City of Courtenay (read 2026-11-05)
  2. Building and plumbing permits, City of Courtenay (read 2026-11-05)
  3. Inspections, City of Courtenay (read 2026-11-05)

Checked by script, not yet by a person: the official wording behind 6 of 6 facts was matched to the official text. How answers are checked.