Lillooet building permit fees
How much does a building permit cost in Lillooet?
In Lillooet the building permit fee is $200 for work valued up to $1,000, plus $6.50 for each additional $1,000. You also pay a $50 application fee and a plan processing fee when you apply; both are credited toward the permit fee. Fees double if work starts before a permit.
Key facts
| Lowest fee | $200 for construction value of $1 to $1,000. The $50 application fee and the plan processing fee ($150 or $250), paid when applying, are credited toward the permit fee.Fees and Charges Bylaw No. 2021-003, current to April 22, 2026, Schedule 4, s. 3.0 · Wording matched the official text retrieved 2026-11-08Official wordingConstruction Value $1.00 to $1,000.00 $200.00 Applied to Permit Fee Total |
|---|---|
| How the fee is worked out | $200 for the first $1,000 of construction value, plus $6.50 for each $1,000 over that. For a house, the value is the greater of your declared value or the District's per-m² table (one storey $1,884, finished basement $807, sundeck $430, secondary suite $1,345).Fees and Charges Bylaw No. 2021-003, current to April 22, 2026, Schedule 4, s. 3.0; Building Bylaw 2021-006, consolidated to June 4, 2025, s. 2.3 (definition of "value of the work") · Wording matched the official text retrieved 2026-11-08Official wordingFor each $1,000.00 over $1,000.00 +$6.50 One Storey $1,884.00 Finished Basement $807.00 Sundeck (no roof) $430.00 Secondary Suite $1,345.00 Value of Work Table The declared value of the work; or The value pursuant to the District of Lillooet Fees & Charges Bylaw; |
| Application or plan review fee | $50 non-refundable application fee (applied to the permit fee total), plus a plan processing fee due at application: $150 for a simple building up to 99.9 m², $250 for 100 m² and greater; complex building $150 plus 25% of the permit fee. The plan processing fee is credited against the permit fee.Fees and Charges Bylaw No. 2021-003, current to April 22, 2026, Schedule 4, s. 1.0; Building Bylaw 2021-006, consolidated to June 4, 2025, s. 10.5.2 · Wording matched the official text retrieved 2026-11-08Official wordingApplied to Permit Fee Total Non-Refundable Application Fee $50.00 Plan Processing Fee - due at time of application up to 99.9m2 $150.00 100m2 and greater $250.00 Complex Building, per building $150.00 + collected when the permit is issued, minus the $150 plan processing fee The plan processing fee is non-refundable and shall be credited against the building permit fee when the permit is issued; |
| Other fees | Plumbing permit $50 plus $10 per extra fixture; demolition $150; excavation $250; re-inspection $100; renewal $100. Security deposit with the application: $1,000 (addition, alteration, renovation, demolition, pool, or accessory building over 25 m²), $2,500 (new house or simple building), $5,000 (complex building). Work started before a permit: the greater of +$500 or double the fee.Fees and Charges Bylaw No. 2021-003, current to April 22, 2026, Schedule 4, ss. 2.0, 4.0, 5.0; Building Bylaw 2021-006, consolidated to June 4, 2025, s. 10.6.1 · Wording matched the official text retrieved 2026-11-08Official wordingMinimum Fee for any Plumbing Permit or First Fixture $50.00 Demolition Permit $150.00 Building or Structure Excavation Permit $250.00 Building or Structure Re-Inspection Fee, per re-inspection $100.00 Permit Renewal Fee, for additional 12 months $100.00 Addition to building permit fee +$500.00 Permit Fee x 2 to a maximum of an additional $10,000.00 For a new single family dwelling or simple building: $2,500.00 For a complex building: $5,000.00 For a single family dwelling addition, alteration, renovation, demolition: $1,000.00 a swimming pool or an accessory building greater than 25 square metres: $1,000.00 |
| How to pay | The $50 application fee and plan processing fee are due when applying. The permit fee and any other District charges must be paid before the permit is issued.Fees and Charges Bylaw No. 2021-003, current to April 22, 2026, Schedule 4, s. 1.0; Building Bylaw 2021-006, consolidated to June 4, 2025, s. 10.5.1 · Wording matched the official text retrieved 2026-11-08Official wordingPlan Processing Fee - due at time of application Before receiving a building permit for a building or structure, the owner must first pay to the District: The building permit fee prescribed in the District’s Fees & Charges |
| Bylaw | Fees and Charges Bylaw No. 2021-003, Schedule 4 (Building Permit and Regulation Fees), current to April 22, 2026; Building Bylaw 2021-006, s. 10.5.Fees and Charges Bylaw No. 2021-003, current to April 22, 2026, Schedule 4; Building Bylaw 2021-006, consolidated to June 4, 2025, s. 10.5 · Wording matched the official text retrieved 2026-11-08Official wordingFees and Charges Bylaw No. 2021-003 Current to April 22, 2026 4 Building Permit and Regulation Fees Building Permit Fees & Charges |
How it works
Fees are set in Schedule 4 (Building Permit and Regulation Fees) of the District's Fees and Charges Bylaw No. 2021-003, with rules in section 10.5 of the Building Bylaw 2021-006. The permit fee is $200 for the first $1,000 of construction value, plus $6.50 for each $1,000 over that.
For a house, the value is the greater of your declared value or the District's per-m² table: one storey $1,884, finished basement $807 and sundeck $430, secondary suite $1,345. Other rows include each additional storey $1,076/m², renovations $807/m², attached garage $807/m², detached garage $700/m² (non-heated) or $1,076/m² (heated), roof only $323/m² and carport $377/m².
Steps
- Pay the $50 non-refundable application fee when you apply. It is credited toward the permit fee.
- Pay the plan processing fee at the same time: $150 for a simple building up to 99.9 m², $250 for 100 m² and greater, or $150 plus 25% of the permit fee for a complex building. It is also credited toward the permit fee.
- Pay the permit fee and any other District charges before the permit is issued.
Good to know
- Other fees: plumbing permit $50 plus $10 per extra fixture; demolition $150; excavation $250; re-inspection $100; renewal $100.
- Security deposit with the application: $1,000 for an addition, alteration, renovation, demolition, pool or accessory building over 25 m²; $2,500 for a new house or simple building; $5,000 for a complex building.
- If work starts before a permit, the fee is the greater of an extra $500 or double the fee.
- An application is cancelled and the plan processing fee forfeited if the permit is not issued and paid within 180 days of notice that it is ready.
- Fire suppression, alarm, masonry, retaining wall and pool permits have their own fees. Ask the Building Official at building@lillooet.ca.
Official forms and pages
The same question in other places
Ashcroft · Cache Creek · Logan Lake · Lytton · Pemberton · Whistler
Sources
- Fees and Charges Bylaw No. 2021-003, current to April 22, 2026, District of Lillooet (read 2026-11-08)
- Building Bylaw 2021-006, consolidated to June 4, 2025, District of Lillooet (read 2026-11-08)
- Building Permits, District of Lillooet (read 2026-11-08)
Checked by script, not yet by a person: the official wording behind 6 of 6 facts was matched to the official text. How answers are checked.