Short answer

In Sechelt a building permit fee is based on the value of the work, starting at $210 for work up to $1,000. A non-refundable application fee is paid when you apply and credited to the permit fee. Rates are in Schedule F of the Fees and Charges Bylaw.

Key facts

Lowest fee$210 for work valued up to $1,000. But the minimum building permit application fee is $580 for a new single-family building, $3,150 for a new multi-family building and $2,360 for a new commercial or industrial building. For other permits it is 50% of the estimated permit fee, to a maximum of $580.Fees and Charges Bylaw No. 575, 2019 (PDF, consolidated March 2026), Schedule F, item 1 · Wording matched the official text retrieved 2026-11-06
Official wording
1(a) $ 0 to $1,000 $210.00
Minimum building permit application fee for 1(a) $580.00 a new single-family building
1(b) $3150.00 a new multi-family building
1(c) $2360.00 a new commercial or industrial building
50% of the estimated building Minimum building permit application fee for 1(d) permit fee to a maximum of other permits $580.00
How the fee is worked outBased on the value of the work. $210 up to $1,000; $210 plus $16.65 per $1,000 (or part) over $1,000 up to $10,000; $359.85 plus $14.30 up to $30,000; then lower rates in further tiers, to $7,180.85 plus $9.25 per $1,000 over $700,000. The building official sets the value, using Marshall Swift costs or other acceptable means.Fees and Charges Bylaw No. 575, 2019 (PDF, consolidated March 2026), Schedule F, items 1-2 · Wording matched the official text retrieved 2026-11-06
Official wording
$210.00 plus $16.65 for each 1(b) $ 1,001 to $10,000 $1,000 or part thereof over $1,000
$359.85 plus $14.30 for each 1(c) $10,001 to $30,000
$7,180.85 plus $9.25 for each 1(g) $700,001 and over $1,000 or part thereof over $700,000
The value of work under a permit shall be the value accepted or determined by the building official
Application or plan review feeAn application fee is paid when applying. It is set in Schedule F as the minimum application fee above, is non-refundable, and is credited against the permit fee when the permit is issued. The application is cancelled and the fee forfeited if the permit is not issued and paid for within 90 days of notice that it is ready.Building Bylaw No. 409, 2003 (PDF, consolidated February 3, 2022), ss. 8.3-8.5 · Wording matched the official text retrieved 2026-11-06
Official wording
An application made for a building permit shall be accompanied by the appropriate application fee as set out in Schedule “F”
The application fee is non-refundable and shall be credited against the building permit fee
within 90 days of the date of written notification to the owner or agent that the permit is ready to be issued
Other feesSchedule F: revised plans $260; demolition $370 (single-family or two-unit) or $830 (other); re-inspection after two rejections $290; after-hours inspection from $1,050; unregistered suite conversion $290. Plumbing permit (Schedule G): minimum $68.25. Security deposit: 1% of construction value over $20,000 (maximum $50,000); $2,625 for a new single-family home.Fees and Charges Bylaw No. 575, 2019 (PDF, consolidated March 2026), Schedule F, items 3-20 · Wording matched the official text retrieved 2026-11-06
Official wording
Revision of approved plans $260.00
4(a) Single family or two-unit dwelling $370.00
4(b) Other Buildings $830.00
$1082.00
Minimum fee per flue payable for the 6 erection, addition, alteration, or repair of a $100.00
8 $290.00
Minimum of $1,050.00
Conversion of an unregistered secondary 11 $290.00
Deposit for construction of a new single $2,625.00
1% of the construction value temporary building or above to a maximum of $50,000.00
SCHEDULE G: PLUMBING AND SPRINKLER PERMIT
Minimum fee for a permit $68.25
Deposit for construction of a new single
How to payThe permit fee must be paid in full before the permit is issued. Fees can be paid online through Cloudpermit's secure payment portal.Building Bylaw No. 409, 2003 (PDF, consolidated February 3, 2022), s. 8.1; Building Permits, How do I get a building permit? · Wording matched the official text retrieved 2026-11-06
Official wording
shall be paid in full prior issuance of any permit under this bylaw
Pay online for permits through a secure payment portal;
BylawFees and Charges Bylaw No. 575, 2019, Schedule F (Building Permit Fees and Deposits); fees are required by Building Bylaw No. 409, 2003, Part 8Fees and Charges Bylaw No. 575, 2019 (PDF, consolidated March 2026), Schedule F; Building Permits, Fees · Wording matched the official text retrieved 2026-11-06
Official wording
SCHEDULE F: BUILDING PERMIT FEES AND DEPOSITS
Building Fees can be found on Schedule F of our Fees and Charges Bylaw No. 575, 2019

How it works

The District of Sechelt sets building permit fees in Schedule F of the Fees and Charges Bylaw 575. The fee is based on the value of the work, which the building official sets using Marshall Swift costs or other acceptable means. Building Bylaw 409 Part 8 requires the fees to be paid.

Rates in Schedule F:

  • Up to $1,000: $210.
  • $1,001 to $10,000: $210 plus $16.65 per $1,000 (or part) over $1,000.
  • $10,001 to $30,000: $359.85 plus $14.30.
  • $30,001 to $50,000: $645.85 plus $12.00.
  • $50,001 to $100,000: $885.85 plus $10.70.
  • $100,001 to $700,000: $1,420.85 plus $9.60.
  • Over $700,000: $7,180.85 plus $9.25.

Each rate is per $1,000 or part over the start of that tier.

Steps

  1. Apply through Cloudpermit and pay the application fee.
  2. The fee is credited against the permit fee when the permit is issued.
  3. Pay the permit fee in full through Cloudpermit's payment portal before the permit is issued.

Good to know

  • The application fee is non-refundable. The minimum is $580 for a new single-family building, $3,150 for a new multi-family building and $2,360 for a new commercial or industrial building. For other permits it is 50% of the estimated permit fee, to a maximum of $580.
  • The application is cancelled and the fee forfeited if the permit is not issued and paid for within 90 days of notice that it is ready.
  • Other Schedule F fees: revised plans $260; demolition $370 (single-family or two-unit) or $830 (other); re-inspection after two rejections $290; after-hours inspection from $1,050; unregistered suite conversion $290.
  • Plumbing permits are under Schedule G, with a minimum of $68.25.
  • Security deposit: 1% of construction value over $20,000 (maximum $50,000); $2,625 for a new single-family home.
  • Bylaw 409 s. 8.2 reduces the permit fee by 10% (to a maximum of $1,000) when a permit is issued under Part 7.

Official forms and pages

The same question in other places

Gibsons · Bowen Island · Nanaimo · Lions Bay · West Vancouver · Parksville

Building permit fees in British Columbia, by municipality →

Sources

  1. Fees and Charges Bylaw No. 575, 2019 (PDF, consolidated March 2026) (read 2026-11-06)
  2. Building Bylaw No. 409, 2003 (PDF, consolidated February 3, 2022) (read 2026-11-06)
  3. Building Permits, District of Sechelt (read 2026-11-06)

Checked by script, not yet by a person: the official wording behind 6 of 6 facts was matched to the official text. How answers are checked.