Nanaimo building permit fees
How much does a building permit cost?
A City of Nanaimo building permit costs $105 for the minimum and the first $1,000 of construction value, plus $10 per $1,000 up to $100,000 and $7 per $1,000 above that. Plumbing and other fees are extra. Jobs over $20,000 pay a 10 percent application fee up front.
Key facts
| Lowest fee | $105, which covers the minimum fee and the first $1,000 of construction value.Fees and Charges Bylaw 2021 No. 7336 (PDF, consolidated 2026-JUN-01), Schedule A, Development Services Fees, Building Inspection Section · Wording matched the official text retrieved 2026-11-06Official wordingMinimum fee and first $1000 of Construction Value (CV) $105 |
|---|---|
| How the fee is worked out | $105 for the first $1,000 of construction value, plus $10 per $1,000 from $1,000.01 to $100,000, plus $7 per $1,000 above $100,000. A 5% reduction applies when an architect or engineer provides a Letter of Assurance and the inspector confirms in writing that the City is relying on it.Fees and Charges Bylaw 2021 No. 7336 (PDF, consolidated 2026-JUN-01), Schedule A, Building Permit Value of Construction · Wording matched the official text retrieved 2026-11-06Official wordingMinimum fee and first $1000 of Construction Value (CV) $105 Additional fee for CV from $1,000.01 - $100,000 $10/$1,000 Additional fee for CV from $100,000.01 - Greater $7/$1,000 Five percent reduction in the |
| Application or plan review fee | When the estimated construction value is over $20,000, an application fee of 10% of the estimated building permit fee (minimum $175) is paid at application. It counts toward the permit fee, but the City keeps it if you do not proceed with the project.Fees and Charges Bylaw 2021 No. 7336 (PDF, consolidated 2026-JUN-01), Schedule A, Application Fees · Wording matched the official text retrieved 2026-11-06Official wordingof construction exceeds $20,000 shall pay 10 percent of the issuance - minimum $175 The fee paid shall be applied towards the total cost of the with the project, the City will retain the fee. |
| Other fees | Plumbing permit $40 minimum plus $8 per fixture. Re-inspection $150. Special inspection of an existing building $100. Permit renewal $100 (value up to $50,000) or $250. Bond for new residential construction $750, refundable after occupancy approval if City property is undamaged. Pre-2005 suite authorization $500 minimum. Accelerated single-family review $150 surcharge.Fees and Charges Bylaw 2021 No. 7336 (PDF, consolidated 2026-JUN-01), Schedule A, Building Inspection Section; Residential Building Permit Application Guide, Charges for a Building Permit, Bond Fee · Wording matched the official text retrieved 2026-11-06Official wordingMinimum Charge $40 Per fixture (includes swimming pools, interceptors, hot water $8 shall be $150. The fee for a requested inspection of an existing building. $100 $0 - $50,000 $100 $50,000.01 - greater $250 Where a permit is required in order to authorize an illegal suite $500 minimum may request that the Building Permit review be accelerated. Refundable after occupancy approval, providing there is no damage to City services, roads, sidewalks, etc. |
| How to pay | The application fee (for work over $20,000) is requested after the online application is accepted; the remainder of the fees must be paid before the permit is issued. The pages read do not say which payment methods are accepted for building permits.Fees and Charges Bylaw 2021 No. 7336 (PDF, consolidated 2026-JUN-01), Schedule A, Application Fees; Residential Building Permit Application Guide, Application Requirements · Wording matched the official text retrieved 2026-11-06Official wordingThe remainder of the applicable fees shall be payable prior to issuance of a Building Permit. The application fee will be requested after your online BP application has been accepted. |
| Bylaw | Fees and Charges Bylaw 2021 No. 7336, Schedule A (Development Services Fees, Building Inspection Section)Fees and Charges Bylaw 2021 No. 7336 (PDF, consolidated 2026-JUN-01), s. 1 and 2, Schedule A · Wording matched the official text retrieved 2026-11-06Official wordingThis Bylaw may be cited as "Fees and Charges Bylaw 2021 No. 7336". BUILDING INSPECTION SECTION |
How it works
The City of Nanaimo sets building permit fees in Schedule A of the Fees and Charges Bylaw. The main fee depends on the value of the construction. The City's Building Permit Fee Calculator gives a rough figure only; it leaves out connection, plumbing fixture and sprinkler fees.
Main fee
- $105 covers the minimum fee and the first $1,000 of construction value.
- $1,000.01 to $100,000: add $10 per $1,000.
- Over $100,000: add $7 per $1,000.
- If an architect or engineer provides a Letter of Assurance and the inspector confirms in writing that the City relies on it, the fee is reduced by 5 percent.
Other fees
- Application fee: when the estimated construction value is over $20,000, 10 percent of the estimated permit fee (minimum $175) is paid at application. It counts toward the permit fee, but the City keeps it if you do not proceed.
- Plumbing permit: $40 minimum plus $8 per fixture.
- Re-inspection: $150. Special inspection of an existing building: $100.
- Permit renewal: $100 (work valued up to $50,000) or $250.
- Bond for new residential construction: $750, refundable after occupancy approval if City property is undamaged.
- Accelerated single-family review: $150 surcharge.
- Authorizing a suite built before 2005: $500 minimum.
Good to know
- The application fee is requested after the online application is accepted; the rest is paid before the permit is issued. The City's pages do not say which payment methods are accepted, so ask Building Inspections.
- Demolition, moving, sign, sprinkler and service pipe fees are also in the schedule.
- Development Cost Charges and School Site Acquisition Charges are separate.
Official forms and pages
The same question in other places
Ladysmith · Parksville · Sechelt · Qualicum Beach · Lake Cowichan · Gibsons
Sources
- Fees and Charges Bylaw 2021 No. 7336 (PDF, consolidated 2026-JUN-01) (read 2026-11-05)
- Building Permit Fee Calculator, City of Nanaimo (read 2026-11-05)
- Residential Building Permit Application Guide (PDF) (read 2026-11-05)
Checked by script, not yet by a person: the official wording behind 6 of 6 facts was matched to the official text. How answers are checked.