100 Mile House building permit fees
How much does a building permit cost?
In 100 Mile House a building permit costs $200 plus $10 per $1,000 of construction value up to $200,000, and $6 per $1,000 of the part over $200,000. A separate $200 non-refundable application fee is also charged.
Key facts
| Lowest fee | $200 for work valued at $1.00 to $1,000, plus the separate $200 non-refundable application fee.Fees and Charges Bylaw No. 1434, 2024, Schedule C, Schedule C, s. 3(a) · Wording matched the official text retrieved 2026-11-08Official wording(a) $ 1.00 to $ 1,000; $200.00 The building permit fee is in addition to this non-refundable application fee. (a) $ 1.00 to $ 1,000; |
|---|---|
| How the fee is worked out | Based on estimated construction value: $200 plus $10 per $1,000 of value up to $200,000; over $200,000, that amount plus $6 per $1,000 of the excess. Value for houses, garages and similar is set by the Building Inspector using RS Means square-foot costs.Fees and Charges Bylaw No. 1434, 2024, Schedule C, Schedule C, s. 3 and s. 13 · Wording matched the official text retrieved 2026-11-08Official wording(b) $ 1,000 to $ 200,000 $200 plus $10.00 per $1,000 up to $200,000 As (b) above then $6.00 per $1,000 value construction of excess of $200,000 As determined by the Building Inspector through application of the RS Means |
| Application or plan review fee | $200 non-refundable application fee on all permits except where the permit fee is less than $200; the permit fee is charged in addition. For anything other than a single-family dwelling or its accessory building, a plan processing fee of 50% of the estimated permit fee, up to $2,000.Fees and Charges Bylaw No. 1434, 2024, Schedule C, Schedule C, s. 1(a) and s. 2 · Wording matched the official text retrieved 2026-11-08Official wordingthe building permit fee is less than the application fee. The building permit fee is in addition to this non-refundable application fee. the plan processing fee shall be fifty percent (50%) the plan processing fee shall not exceed $2000.00 |
| Other fees | Plumbing permit $200 (includes 1 fixture), then $10 per extra fixture; residential demolition $150; chimney or new solid fuel appliance $150; restoration and clean-up security $500 residential, $2,500 commercial; re-plan checking $500; work started without a permit (stop-work order posted): double fee, extra capped at $750.Fees and Charges Bylaw No. 1434, 2024, Schedule C, Schedule C, s. 1, 5, 11, 12 · Wording matched the official text retrieved 2026-11-08Official wordingBasic Plumbing Permit - includes 1 fixture (minimum fee) $ 200.00 $ 10.00 per fixture after first fixture a. Residential Building $150.00 (c) Installation of a chimney or a new solid fuel appliance $ 150.00 (a) Commercial construction $ 2,500.00 (b) Residential construction $ 500.00 Re-Plan Checking Fee - $500.00 the applicant shall pay double the building permit fee prescribed in this Schedule provided that the additional fee shall not exceed: $ 750.00 |
| How to pay | The plan processing fee accompanies the application. The permit fee is paid to the Building Inspector before the permit is issued; the District phones the applicant with the fees when the permit is ready. A plan processing fee is forfeited if the permit is not secured and fully paid within 30 days of notification.Building Bylaw No. 695, 1996 consolidation, s. 5.4.1, 5.4.3, 5.5.1; Building Permits, Building Permits page · Wording matched the official text retrieved 2026-11-08Official wordingAn application for a permit shall be accompanied by the appropriate plan has not been secured and entirely paid for within thirty days of notification shall first pay to the Building Inspector the appropriate permit fee the applicant will receive a phone call notifying that the permit has been issued and what the fees are. |
| Bylaw | Fees and Charges Bylaw No. 1434, 2024, Schedule C (Building Permits)Fees and Charges Bylaw No. 1434, 2024, Schedule C, cover and Schedule C · Wording matched the official text retrieved 2026-11-08Official wordingFees and Charges Bylaw No. 1434, 2024 Schedule "C" - Building Permits |
How it works
Fees are in Schedule C of the District's Fees and Charges Bylaw No. 1434. The permit fee is based on the estimated value of construction: $200 plus $10 per $1,000 of value up to $200,000. Over $200,000, add $6 per $1,000 of the excess. For houses, garages and similar buildings, the Building Inspector sets the value using RS Means square-foot costs.
Work valued at $1.00 to $1,000 has a $200 fee, plus the separate application fee.
Steps
- Pay the $200 non-refundable application fee when you apply. It applies to all permits except where the permit fee is less than $200. The permit fee is charged in addition.
- For anything other than a single-family dwelling or its accessory building, a plan processing fee of 50% of the estimated permit fee, up to $2,000, accompanies the application.
- The District phones you with the fees when the permit is ready. Pay the Building Inspector before the permit is issued.
Good to know
- Other fees: plumbing permit $200 (includes 1 fixture), then $10 per extra fixture; residential demolition $150; chimney or new solid fuel appliance $150; re-plan checking $500.
- Restoration and clean-up security is $500 for residential and $2,500 for commercial work. The Building Permits page says clean-up bonds are refundable upon final inspection.
- Starting work without a permit (stop-work order posted) doubles the fee, with the extra capped at $750.
- A plan processing fee is forfeited if the permit is not secured and fully paid within 30 days of notification.
- The Building Permits page also lists a $50 minimum plan processing fee that is not in the bylaw. The bylaw is followed here; confirm with the District.
Official forms and pages
The same question in other places
Williams Lake · Cache Creek · Barriere · Clearwater · Ashcroft · Lillooet
Sources
- Fees and Charges Bylaw No. 1434, 2024, Schedule C (PDF), District of 100 Mile House (read 2026-11-08)
- Building Bylaw No. 695, 1996 consolidation (PDF), District of 100 Mile House (read 2026-11-08)
- Building Permits, District of 100 Mile House (read 2026-11-08)
Checked by script, not yet by a person: the official wording behind 6 of 6 facts was matched to the official text. How answers are checked.