Armstrong building permits: when you need one and how to apply
Do I need a building permit, and how do I apply?
In the City of Armstrong, a building permit is needed for most construction, including structural changes, demolition, plumbing, pools and hot tubs, and new secondary suites. Apply at City Hall, 3535 Bridge Street, with Form A and a complete package. Payment must come with it.
Key facts
| Needed for | Most construction: building, repairing or altering a building or structure, moving or demolishing one, occupying a new building, plumbing, fire alarm or sprinkler work, wood-burning appliances, signs, retaining walls over 1.2 m, pools, hot tubs and their fences, new secondary or accessory suites, and any structural change.Building Bylaw No. 1903, 2022, s. 7.1; A Guide to Building Permits (March 2023) · Wording matched the official text retrieved 2026-11-06Official wordingevery owner shall apply for and obtain a permit prior to: constructing, repairing or altering a building or structure; constructing, repairing or altering a retaining wall greater than 1.2 meters in height. constructing swimming pools, hot tub installation, and swimming pool fences; constructing a new secondary or accessory suite; any structural change, alteration, or repair to any building or structure; A building permit is required for most types of construction, with a few exceptions. |
|---|---|
| Not needed for | Accessory building with no plumbing under 10 m² that creates no hazard; trellises, arbours and soil-retaining walls under 1.2 m on single-family residential lots (no hazard); fences the zoning bylaw permits (pool fences still need a permit); decks less than 0.6 m above ground, sited per zoning; non-structural repair or maintenance; clearing pipe stoppages or like-for-like fixture replacement.Building Bylaw No. 1903, 2022, s. 3.4 · Wording matched the official text retrieved 2026-11-06Official wordingThis bylaw does not apply to: an accessory building without plumbing less than 10 square metres in building area that does not create a hazard; a wall supporting soil less than 1.2 metres in height except as set out in Part 12 of this bylaw, a fence permitted to be constructed under the City’s zoning bylaw; deck additions, except a deck where the difference in elevation between the deck surface and the ground surface at any point is 0.6 metres or more non-structural repair, alteration or maintenance of lawfully conforming structures |
| How to apply | Fill in the permit application (Form A) and bring the complete package, with payment, to City Hall (3535 Bridge Street). Forms are available at City Hall and online. An electronic copy of the plans can be emailed to info@cityofarmstrong.bc.ca. No online portal found. Credit cards not accepted.A Guide to Building Permits (March 2023); Building Permit Application Checklist · Wording matched the official text retrieved 2026-11-06Official wordingBuilding Permit applications are available at City Hall and online. Credit Card payments are not accepted. ONLY COMPLETE BUILDING APPLICATION PACKAGES WILL BE ACCEPTED. Payment must accompany the application. 3535 Bridge Street Electronic Copy of Construction and Site Plan, submitted on a thumb drive or emailed to |
| What to submit | Application (Form A) and fee; signed Acknowledgement of Responsibilities (Form B); title search under 30 days old; BC Energy Compliance Report; BC Housing builder licensing or owner-builder documents for dwellings; site plan; two sets of metric construction drawings; electronic copy. Engineer reports (geotechnical, foundation) may be required.Building Permit Application Checklist; Building Bylaw No. 1903, 2022, s. 10.1 · Wording matched the official text retrieved 2026-11-06Official wordingCompleted and signed Acknowledgement of Responsibilities. (Form B). Title Search (less than 30 days old) BC Housing Builder Licensing documents are required for all dwellings Two (2) Complete Sets of Construction Drawings (in METRIC) Electronic Copy of Construction and Site Plan NOTE: Some specific documents not listed above may also be required. include a copy of a title search for the relevant property dated within 30 days of the |
| Processing time | Generally about 3 weeks after a complete application is submitted (checklist). The 2023 guide says normally 3 to 4 weeks. It depends on completeness and the time of year.Sources differ: Two City documents differ slightly (3 weeks vs 3 to 4 weeks). The checklist is newer (file list dated 2026-08-27), the guide is dated March 2023.Building Permit Application Checklist; A Guide to Building Permits (March 2023) · Wording matched the official text retrieved 2026-11-06Official wordingThe estimated turnaround time is generally 3 weeks after the completed application is submitted. The building permit application process normally takes 3-4 weeks to complete. |
| Inspections | Give the Building Official at least 48 hours' notice, not counting weekends and statutory holidays, by phone or in writing, before an inspection. For a simple building, get the inspector's written acceptance before covering work.Building Bylaw No. 1903, 2022, s. 7.22, 10.33, 10.34; A Guide to Building Permits (March 2023) · Wording matched the official text retrieved 2026-11-06Official wordingevery owner must give at least 48 hours’ notice, not including weekends and statutory holidays, to the Building Official: the owner must give at least 48 hours’ notice, has requested the inspection by phone or in writing in accordance with this The applicant is to contact the Building Inspector a minimum of 48 hours prior to needing an inspection. |
| Contact | City of Armstrong Building Inspection Services, City Hall, 3535 Bridge Street; phone 250-546-3023; email inspector@cityofarmstrong.bc.ca (Building Official) or info@cityofarmstrong.bc.ca.Planning and Development Services, Contact Us; Building Permit Application Checklist · Wording matched the official text retrieved 2026-11-06Official wordingQuestions about building permits or the BC Building Code inspector@cityofarmstrong.bc.ca Building Inspection Services PO Box 40 | 3535 Bridge Street Armstrong, BC V0E 1B0 P: 250.546.3023 | F: 250.546.3710 PO Box 40 | 3535 Bridge Street Armstrong, BC V0E 1B0 P: 250.546.3023 | F: 250.546.3710 Email: info@cityofarmstrong.bc.ca Website: www.cityofarmstrong.bc.ca |
| Bylaw | City of Armstrong Building Bylaw No. 1903, 2022Building Bylaw No. 1903, 2022, s. 1 · Wording matched the official text retrieved 2026-11-06Official wordingThis bylaw may be cited as “City of Armstrong Building Bylaw No. 1903, 2022”. |
How it works
Under the Building Bylaw 1903, 2022, an owner must get a permit before building, repairing or altering a building or structure, moving or demolishing one, or any structural change. A permit is also required for plumbing, fire alarm or sprinkler work, wood-burning appliances, signs, retaining walls over 1.2 m, swimming pools, hot tubs and their fences, and a new secondary or accessory suite.
You do not need a building permit for an accessory building without plumbing under 10 m² that creates no hazard, trellises and arbours, a soil-retaining wall under 1.2 m on a single-family lot, a fence the zoning bylaw permits (pool fences still need one), a deck less than 0.6 m above ground that meets zoning, or non-structural repair and maintenance.
Steps
- Check zoning with City Hall before you design.
- Fill in Form A and gather the items on the Building Permit Application Checklist.
- Bring the complete package, with payment, to City Hall. Forms are available at City Hall and online. Only complete packages are accepted. Credit cards are not accepted.
- After the permit is issued, give the Building Official at least 48 hours' notice, not counting weekends and statutory holidays, by phone or in writing before each inspection.
- For a simple building, get the inspector's written acceptance before covering work.
Good to know
- Gas and electrical permits are separate and come from the Province.
- Fees double if work starts before the permit is issued.
- Processing time: the 2023 guide says 3 to 4 weeks and the newer checklist says about 3 weeks. Ask City Hall for the current time.
- No online application portal was found; the City's permit forms are on its CivicWeb document centre.
What you'll need
- Form A (permit application) and the fee
- Form B (signed Acknowledgement of Responsibilities)
- Title search less than 30 days old
- Site plan and two sets of metric construction drawings, plus an electronic copy
- BC Energy Compliance Report
- For dwellings, BC Housing builder licensing or owner-builder documents
- An engineer's report (geotechnical or foundation) if the City asks for one
Official forms and pages
The same question in other places
Spallumcheen · Enderby · Vernon · Coldstream · Lumby · Lake Country
Building permits in British Columbia: how to apply, by municipality →
Sources
- Building Bylaw No. 1903, 2022 (PDF), City of Armstrong (read 2026-11-05)
- A Guide to Building Permits (March 2023), City of Armstrong (read 2026-11-05)
- Building Permit Application Checklist, City of Armstrong (read 2026-11-05)
- Permits folder, City of Armstrong CivicWeb (read 2026-11-05)
- Rates, Fees and Charges Bylaw No. 1916, 2023 (PDF, consolidated to Bylaw 1947, 2026), City of Armstrong (read 2026-11-05)
- Planning and Development Services, City of Armstrong (read 2026-11-05)
Checked by script, not yet by a person: the official wording behind 8 of 8 facts was matched to the official text. How answers are checked.