Spallumcheen building permits: when you need one and how to apply

Do I need a building permit in Spallumcheen, and how do I apply?

Spallumcheen, British ColumbiaChecked against official textSources read 2026-11-06

Short answer

In the Township of Spallumcheen, you need a building permit for any construction, addition, alteration, change of use or demolition. Apply in person at the Township office with paper copies; electronic and incomplete applications are not accepted. Email planner@spallumcheentwp.bc.ca to book an appointment first.

Key facts

Needed forAny construction, addition, alteration, change of use or demolition of a building or structure. A permit is also required before installing plumbing, a new chimney or solid-fuel appliance, or moving a building or manufactured home onto a lot.Building, Building page; Building Bylaw No. 2009, 2020 (PDF, consolidated), s. 601.1 · Wording matched the official text retrieved 2026-11-06
Official wording
A building permit is required for any construction, addition, alteration, change of use or demolition of a building or structure.
Every owner shall apply for and obtain a permit before:
installing plumbing systems related to the inspections undertaken pursuant to this
constructing a new masonry chimney, installing a new metal chimney for a solid
Not needed forAccessory buildings under 10 m² that create no hazard and meet zoning. In S.H., C.R., A.2 and L.H. zones: accessory and agricultural buildings under 55 m², one storey (6 m), no plumbing, meeting zoning. Also retaining structures 1.2 m or less, fences, non-structural repairs, and decks under 0.6 m above ground (sited per zoning).Building Bylaw No. 2009, 2020 (PDF, consolidated), s. 105.2 · Wording matched the official text retrieved 2026-11-06
Official wording
accessory buildings less than 10 square metres in building area that do not
accessory and agricultural buildings which are less than 55 m2 in size, are no
Small Holdings (S.H.), Country
Residential (C.R.), Agricultural (A.2), and Large Holdings (L.H.)
retaining structures 1.2 metres in height or less;
e. fences;
non-structural repairs or alterations to a building or structure or the repair or
deck additions, except a deck where the difference in elevation between the deck
surface and the ground surface at any point is 0.6 metres or more
How to applyIn person at the Township office with paper copies; electronic and incomplete submissions are not accepted. The owner, or an agent the owner authorizes in writing, applies. Book an appointment first by emailing planner@spallumcheentwp.bc.ca.Building, Building page · Wording matched the official text retrieved 2026-11-06
Official wording
The complete application package must be submitted in person with paper copies.
Electronic and incomplete submissions will not be accepted.
book an appointment by emailing planner@spallumcheentwp.bc.ca prior to submitting your application.
The Property Owner is responsible for obtaining a permit, although as the Owner you can authorize an Agent in writing
What to submitThe Building Permit Application Package with its checklist: signed application form, application fee, site plan, two sets of construction plans, title search (within 30 days), Homeowner Protection Act documents for dwellings, access approval, evidence of potable water and sewage disposal, stormwater plan and a pre-construction Energy Advisor report.Building, Building page; Building Bylaw No. 2009, 2020 (PDF, consolidated), s. 701.3; Building Permit Application Package, Application checklist (Required documents), page 2 · Wording matched the official text retrieved 2026-11-06
Official wording
completes and submits the Building Permit Application Package along with all required supporting documentation as shown on the Building Permit Application Checklist.
supplementary contractor information in the form provided by the Township of
confirmation of compliance with the Homeowner Protection Act as applicable;
a copy of a title search made within 30 days of the date of application;
any required highway access permit issued by the Township of Spallumcheen or
Title Search (must be within 30 days prior of application) or Title Search Authorization form and fee
Evidence of potable water supply as outlined in Section 607 of Building Bylaw No. 2009, 2020
Energy Advisor Compliance Report – Pre Construction must be submitted at the time of application and completed by a Certified Energy Advisor
Processing timeNot confirmed. The published pages do not say how long a permit takes.
InspectionsGive at least two working days' notice to book an inspection. Call 250-550-3730 to make an appointment. The inspection schedule is printed on the permit.Building, Building page; Building Bylaw No. 2009, 2020 (PDF, consolidated), s. 903.1 · Wording matched the official text retrieved 2026-11-06
Official wording
An inspection schedule will be provided on your Permit that outlines which inspections are required, and at what stages.
Make sure to provide at least two working days notice to schedule an inspection. To make an appointment call 250-550-3730.
The owner or representative shall give at least two clear working days' notice to the
ContactPlanning and Development Services Department, 250-546-3013, planner@spallumcheentwp.bc.ca. Municipal Office, 4144 Spallumcheen Way, Monday to Friday 8:30 a.m. to 4:30 p.m.Contact Us, Contact page; Building, Building page · Wording matched the official text retrieved 2026-11-06
Official wording
Planning and Development Services Department Phone: 250-546-3013
The Municipal Office is open Monday to Friday, 8:30 am to 4:30 pm
A building permit is required for any construction, addition, alteration, change of use or demolition of a building or structure. Application forms may be picked up at the Township office during regular business hours or found below on our website. The Planning and Development Department is happy to assist you; book an appointment by emailing planner@spallumcheentwp.bc.ca prior to submitting your application.
BylawTownship of Spallumcheen Building Bylaw No. 2009, 2020Building Bylaw No. 2009, 2020 (PDF, consolidated), Title page · Wording matched the official text retrieved 2026-11-06
Official wording
BUILDING BYLAW NO. 2009, 2020
Bylaw No. 2150, 2024

How it works

The Township's Building Bylaw No. 2009, 2020 requires a permit for any construction, addition, alteration, change of use or demolition of a building or structure. A permit is also required before installing plumbing, building a new chimney or solid-fuel appliance, or moving a building or manufactured home onto a lot.

No permit is needed for:

  • Accessory buildings under 10 m² that create no hazard and meet zoning.
  • In the S.H., C.R., A.2 and L.H. zones, accessory and agricultural buildings under 55 m², one storey (6 m), with no plumbing, that meet zoning.
  • Retaining structures 1.2 m or less, fences, non-structural repairs, and decks under 0.6 m above the ground.

These exemptions only apply if the building is sited as the Zoning Bylaw requires. The bylaw lists a few more exemptions (for example some greenhouses, bridges and docks).

Steps

  1. Email planner@spallumcheentwp.bc.ca to book an appointment before you submit.
  2. Put together the Building Permit Application Package and its checklist: signed application form, application fee, site plan, two sets of construction plans, a title search made within 30 days, Homeowner Protection Act documents for dwellings, access approval, evidence of potable water and sewage disposal, a stormwater plan and a pre-construction Energy Advisor report.
  3. Deliver the full paper package in person to the Municipal Office at 4144 Spallumcheen Way, and pay the application fee by cheque or debit. The owner applies, or an agent the owner authorizes in writing.
  4. Township staff review it, then it goes to the Regional District of North Okanagan building inspectors for BC Building Code review.
  5. When the permit is approved, the Township contacts you to come in, pay the permit fees and pick it up.
  6. Your permit carries an inspection schedule. Give at least two working days' notice and call 250-550-3730 to book each inspection.

Good to know

  • Electronic and incomplete submissions are not accepted.
  • A Building Official can require professional design for some work.
  • The Township does not state how long a review takes. Ask Planning at 250-546-3013.

Official forms and pages

The same question in other places

Armstrong · Enderby · Vernon · Coldstream · Lumby · Lake Country

Building permits in British Columbia: how to apply, by municipality →

Sources

  1. Building, Township of Spallumcheen (read 2026-11-06)
  2. Building Bylaw No. 2009, 2020 (PDF, consolidated) (read 2026-11-06)
  3. Building Permit Application Package (PDF) (read 2026-11-06)
  4. Contact Us, Township of Spallumcheen (read 2026-11-06)

Checked by script, not yet by a person: the official wording behind 7 of 8 facts was matched to the official text; 1 could not be confirmed. How answers are checked.