Short answer

In Fruitvale a building permit costs $7 per $1,000 of construction value, or part of it, with a $40 minimum. A non-refundable application fee is applied against the permit fee. Fees are in the Rates, Fees and Charges Bylaw No. 982.

Key facts

Lowest fee$40, which covers about $5,000 of construction value.Rates, Fees and Charges Bylaw No. 982, 2025, Appendix 8, Appendix 8, A · Wording matched the official text retrieved 2026-11-08
Official wording
Minimum fee: $7.00 per $1,000,00 or portion thereof
Minimum of $40.00 covers approximately $5,000 of construction
How the fee is worked out$7 per $1,000 of declared or assessed construction value, or portion thereof, with a $40 minimum. Plumbing fixtures $10 each when issued with a building permit; separately $75 flat plus $10 per fixture.Rates, Fees and Charges Bylaw No. 982, 2025, Appendix 8, Appendix 8, A · Wording matched the official text retrieved 2026-11-08
Official wording
Minimum fee: $7.00 per $1,000,00 or portion thereof
$10.00 per
$75.00 flat rate
Application or plan review feeNon-refundable application fee: the actual permit fee up to $10,000 of construction cost; $50 for $10,000 to $50,000; $150 over $50,000. It is applied against the permit fee.Rates, Fees and Charges Bylaw No. 982, 2025, Appendix 8, Appendix 8, B · Wording matched the official text retrieved 2026-11-08
Official wording
NON-REFUNDABLE APPLICATION FEE
$150.00 for each application valued over $50,000.00.
This fee will be applied against the cost of the permit.
Other feesRe-inspection $75; demolition $50; moving permit $75; temporary building permit $75; mobile or modular home placement $75; minimum inspection fee $50. Renewal: $50 up to $50,000 value, $2 per $1,000 above. Removing a Notice on Title $200. Development permit application $200.Rates, Fees and Charges Bylaw No. 982, 2025, Appendix 8, Appendix 8, C to F · Wording matched the official text retrieved 2026-11-08
Official wording
Re-inspection Fee
Demolition Fee
Moving permit
Minimum Inspection Fee
Construction Value up to $50,000.00
Administrative charge to remove Notice on Title
Development Permit Application**
How to payThe permit fee is paid in full before the permit is issued; the plan-processing fee is paid with the application. Where to pay is not stated.Building and Plumbing Bylaw No. 698, 2003, ss. 16.1, 16.2 · Wording matched the official text retrieved 2026-11-08
Official wording
shall be paid in full prior
An application made for a building permit shall be accompanied by the appropriate
BylawVillage of Fruitvale Rates, Fees and Charges Bylaw No. 982, 2025, Schedule A, Appendix 8 (Planning, Development and Building Permit Fees)Rates, Fees and Charges Bylaw No. 982, 2025, Appendix 8; Rates, Fees and Charges Bylaw No. 982, 2025, Appendix 8, s. 1.1 · Wording matched the official text retrieved 2026-11-08
Official wording
PLANNING, DEVELOPMENT AND BUILDING PERMIT FEES
This Bylaw may be cited as

How it works

Fees are set in Appendix 8 (Planning, Development and Building Permit Fees) of the Village's Rates, Fees and Charges Bylaw No. 982. The permit fee is $7 per $1,000 of declared or assessed construction value, or portion thereof, with a $40 minimum. Plumbing fixtures are $10 each when issued with a building permit. A separate plumbing permit is a $75 flat fee plus $10 per fixture.

A non-refundable application fee is charged on the cost of construction: the actual permit fee up to $10,000; $50 for $10,000 to $50,000; and $150 over $50,000. It is applied against the permit fee.

Other fees

  • Re-inspection: $75
  • Demolition: $50
  • Moving permit: $75
  • Temporary building permit: $75
  • Mobile or modular home placement: $75
  • Minimum inspection fee: $50
  • Renewal: $50 up to $50,000 of value, then $2 per $1,000 above
  • Removing a Notice on Title: $200
  • Development permit application: $200

Good to know

  • Temporary building and mobile home fees are plus the construction values of any new work.
  • Up to 75% of the permit fee may be refunded if construction has not started. A refund under $50 is not made.
  • The permit fee is paid in full before the permit is issued; the plan-processing fee is paid with the application (Bylaw 698). Where to pay is not stated, so ask the Village Office on 250-367-7551.

Official forms and pages

The same question in other places

Montrose · Trail · Warfield · Rossland · Salmo · Castlegar

Building permit fees in British Columbia, by municipality →

Sources

  1. Rates, Fees and Charges Bylaw No. 982, 2025, Appendix 8 (PDF) (read 2026-11-08)
  2. Building and Plumbing Bylaw No. 698, 2003 (PDF) (read 2026-11-08)