Short answer

In Montrose you need a building permit before constructing or altering a building or structure, and for pools, new roofing, moving or demolishing a building, wood-burning appliances and plumbing. The bylaw says apply to the Village; the Village's website says the RDKB issues permits. Confirm with the Village Office first.

Key facts

Needed forA permit is needed before constructing or altering a building or structure, installing a manufactured or modular home or a pool, new roofing, moving a building, demolishing any residential building (or other buildings over 300 m²), masonry fireplaces or wood-burning appliances, and any plumbing work.Building Bylaw (2005-1) No. 633, s. 8.1 · Wording matched the official text retrieved 2026-11-08
Official wording
building permit before constructing or altering a building or
building permit before installation of a pool
plumbing permit before installation, alteration or remodeling of
building permit before new roofing materials are applied to re-
building permit before demolition of all residential buildings and
Not needed forThe bylaw does not apply to: buildings exempted by Part 1 of the Building Code; retaining structures under 1.5 m high; roofless decks no more than 600 mm above grade; existing chimneys; minor plumbing repairs; RVs for temporary use; and seasonal greenhouse-type structures under 28 m².Building Bylaw (2005-1) No. 633, s. 5.2 · Wording matched the official text retrieved 2026-11-08
Official wording
retaining structures less than 1.5 meters (5 ft.) in height;
decks without roofs having a difference in elevation to grade not
exceeding 600 millimeters (2ft.);
that are less than
28 square meters (300 sq. ft.)
How to applyThe bylaw says to apply to the Village, on a form acceptable to the Village. The Village's Permits and Licenses page says building permits are issued by the RDKB and links to an RDCK (Regional District of Central Kootenay) page; it says to visit the Village Office for more information.Sources differ: The bylaw says the Village issues permits; the web page says the RDKB does. The page also links to rdck.ca, which is a different regional district. Confirm with the Village Office before applying.Building Bylaw (2005-1) No. 633, ss. 8.1-8.2; Permits and Licenses, Overview · Wording matched the official text retrieved 2026-11-08
Official wording
must apply for and obtain from the Village a
must be in a form acceptable to the Village.
Building Permits are issued by the RDKB:
Visit the Village Office for more information.
What to submitWhen the building official requires it, a standard-building application includes a site plan (waivable for repairs or alterations), floor plans, cross-section, elevations, a foundation design by a registered professional with letters of assurance, and two sets of drawings. All plans must show the designer's name and address.Building Bylaw (2005-1) No. 633, ss. 8.3, 10.1 · Wording matched the official text retrieved 2026-11-08
Official wording
All plans submitted with permit applications must bear the name and
two sets of drawings at a suitable scale of the design
unless a building official has waived the requirements for a site
When required by the building official, an application for a building per-
Processing timeNot confirmed. The official pages do not state this detail.
InspectionsGive the Village at least 72 hours' notice to request an inspection. Required stages include damp proofing and drain tiles, plumbing, framing, insulation and a final inspection before occupancy. Additions or accessory buildings under 55 m² also need footings inspected.Building Bylaw (2005-1) No. 633, s. 18.4; Building Bylaw Amendment No. 661, s. 18.4.8 · Wording matched the official text retrieved 2026-11-08
Official wording
The owner or his or her representative shall give at least 72 hours' no-
tice to the Village when requesting an inspection
FINAL: When the building or portion thereof is completed and
Any additions or accessory buildings less than 55 square metres
will require that footings be inspected by the building official
ContactVillage Office, 250-367-7234, admin@montrose.ca.Contacts, Village Office; Permits and Licenses, Overview · Wording matched the official text retrieved 2026-11-08
Official wording
565 11th Ave. Montrose, BC V0G 1P0 admin@montrose.ca Phone: 250-367-7234 Fax: 250-367-7288 ### Public Works publicworks@montrose.ca
Box 510 565 11th Ave. Montrose, BC V0G 1P0 admin@montrose.ca Phone: 250-367-7234 Fax: 250-367-7288 ### Public Works
Visit the Village Office for more information.
BylawBuilding Bylaw (2005-1), Bylaw #633, as amended by Bylaw #661 (2007) and Bylaw #719 (2014)Building Bylaw (2005-1) No. 633, s. 1.1; Building Bylaw Amendment No. 719, plumbing, title; Building Bylaw Amendment No. 661, title · Wording matched the official text retrieved 2026-11-08
Official wording
1.0 TITLE 1.1 This Bylaw may be cited for all as the "Building Bylaw (2005-1)." 1.2 The Bylaw is divided into 25 sections and a decimal numbering system
THE CORPORATION OF THE VILLAGE OF MONTROSE BYLAW #633 A BYLAW TO ESTABLISH BUILDING REGULATIONS
THE CORPORATION OF THE VILLAGE OF MONTROSE BYLAW #719 A BYLAW TO AMEND THE BUILDING BYLAW #633(2005-1)
THE CORPORATION OF THE VILLAGE OF MONTROSE BYLAW #661 A BYLAW TO AMEND BUILDING REGULATIONS IN THE VILLAGE OF MONTROSE
AMENDMENT 2. (1) Section 18.0 of bylaw #633 is hereby amended by adding the following inspection requirements:

How it works

Under the Village of Montrose's Building Bylaw 633, you need a permit before constructing or altering a building or structure, installing a manufactured or modular home or a pool, putting on new roofing, moving a building, demolishing any residential building (or other buildings over 300 m²), building a masonry fireplace or installing a wood-burning appliance, and any plumbing work. Starting construction, demolition or moving without a valid permit is not allowed.

The bylaw does not apply to buildings exempted by Part 1 of the BC Building Code, retaining structures under 1.5 m high, roofless decks no more than 600 mm above grade, existing chimneys, minor plumbing repairs, recreational vehicles for temporary use, and seasonal greenhouse-type structures under 28 m².

Steps

  1. Call the Village Office to confirm who issues permits for your project. The bylaw says apply to the Village on a form it accepts, but the Village's website says the RDKB issues building permits.
  2. Prepare your drawings. When the building official requires it, a standard-building application includes a site plan, floor plans, a cross-section, elevations, a foundation design by a registered professional with letters of assurance, and two sets of drawings. All plans must show the designer's name and address.
  3. Residential buildings also need plumbing details, home-warranty insurance and evidence of a licensed builder (s. 13.2).
  4. Pay the fees (see building-permit-fees).
  5. Give the Village at least 72 hours' notice to request each inspection.

Good to know

  • Required inspections include damp proofing and drain tiles, plumbing, framing, insulation and a final inspection before occupancy. Additions and accessory buildings under 55 m² also need footings inspected.
  • Bylaw 719 (2014) changed the timing of the plumbing inspection to when the system is installed but before work that would conceal it.
  • Complex buildings have a longer application list in s. 9.
  • Village Office: 250-367-7234, admin@montrose.ca.

Official forms and pages

The same question in other places

Fruitvale · Trail · Warfield · Rossland · Castlegar · Salmo

Building permits in British Columbia: how to apply, by municipality →

Sources

  1. Building Bylaw (2005-1) No. 633 (PDF), Village of Montrose (read 2026-11-08)
  2. Building Bylaw Amendment No. 661 (PDF), Village of Montrose (read 2026-11-08)
  3. Building Bylaw Amendment No. 719, plumbing (PDF), Village of Montrose (read 2026-11-08)
  4. Permits and Licenses, Village of Montrose (read 2026-11-08)
  5. Contacts, Village of Montrose (read 2026-11-08)

Checked by script, not yet by a person: the official wording behind 7 of 8 facts was matched to the official text; 1 could not be confirmed. How answers are checked.