In Warfield you need a building permit for any construction, alteration, excavation, demolition, removal or relocation of a building or structure, and for retaining walls and swimming pools. The Regional District of Kootenay Boundary (RDKB) Building Department handles permits for the Village: 250-368-9148.
Key facts
| Needed for | A permit is required for any construction, alteration, excavation, reconstruction, demolition, removal, relocation, or change of use or occupancy of a building or structure. Retaining walls and swimming pools also need a building permit.Building Bylaw No. 988, 2026, with backgrounder, ss. 4.1, 5.1, 11.1, 14.1 · Wording matched the official text retrieved 2026-11-08Official wordingA person must not commence or continue any construction, alteration, excavation, A permit is required if work regulated under this bylaw is to be undertaken. No person may construct, or structurally repair, a retaining wall without a building permit. a person must not construct, or structurally repair, a swimming pool without a valid building permit |
|---|---|
| Not needed for | The bylaw does not apply to: a fence (except retaining walls); an accessory building under 10 m² floor area; a trellis, arbour, or wall holding soil under 1.22 m on a single-family residential parcel; and CSA Z240, Z241 or A277 factory-built homes, except as the Building Code regulates.Building Bylaw No. 988, 2026, with backgrounder, s. 3.3 · Wording matched the official text retrieved 2026-11-08Official wordinga fence an accessory building with a floor area of less than 10 square metres a wall supporting soil that is less than 1.22 metres in height except as regulated by the Building Code |
| How to apply | Apply on the form the building official prescribes, signed by the owner. Building permits and inspections are handled for the Village by the Regional District of Kootenay Boundary (RDKB) Building Department (250-368-9148). Village Office: 250-368-8202.Building Bylaw No. 988, 2026, with backgrounder, s. 10.4(a); backgrounder · Wording matched the official text retrieved 2026-11-08Official wordingbe made in the form prescribed by the building official and signed by the owner which for the Village of Warfield are delivered by the Regional District of Kootenay Boundary (RDKB) Building please contact the Regional District of Kootenay Boundary (RDKB) Building Department at 250-368-9148 |
| What to submit | For a simple building: the signed form, the owner's undertaking (Appendix C), a title search less than 30 days old, a BC land surveyor's survey plan (the building official may waive it), and a site plan. Complex buildings need more, including a code summary and architects' or engineers' drawings and letters of assurance.Building Bylaw No. 988, 2026, with backgrounder, ss. 10.2, 10.4 · Wording matched the official text retrieved 2026-11-08Official wordingbe accompanied by the owner’s acknowledgment of responsibility and undertaking include a copy of a title search for the relevant property made within 30 days of the except that the building official may waive the requirement for a survey plan, in whole or in part, where conditions warrant include a building code compliance summary including the applicable edition of the |
| Processing time | Not confirmed. The published pages do not say how long a permit takes. |
| Inspections | Give the Village at least 48 hours' notice when requesting an inspection (online or written notice), and get a building official's written acceptance before concealing work such as footings, framing or insulation. Owners must also give 48 hours' written or online notice before starting work.Building Bylaw No. 988, 2026, with backgrounder, ss. 7.11, 10.26 · Wording matched the official text retrieved 2026-11-08Official wordingFor all work in respect of simple buildings the owner must give at least 48 hours’ notice to the Village when requesting an inspection at least 48 hours prior to commencing work at a building site, give written or online notice to a building official of the date on which the owner intends to |
| Contact | RDKB Building Department 250-368-9148 (permits and inspections); Village Office 250-368-8202.Building Bylaw No. 988, 2026, with backgrounder, Backgrounder · Wording matched the official text retrieved 2026-11-08Official wordingplease contact the Regional District of Kootenay Boundary (RDKB) Building Department at 250-368-9148 please contact the Village of Warfield at 250-368-8202 |
| Bylaw | Village of Warfield Building Bylaw No. 988, 2026Building Bylaw No. 988, 2026, with backgrounder, s. 1.1 · Wording matched the official text retrieved 2026-11-08Official wordingThis bylaw may be cited as “Village of Warfield Building Bylaw No. 988, 2026”. |
How it works
The Village's Building Bylaw No. 988, 2026 requires a permit before anyone starts or continues construction, alteration, excavation, reconstruction, demolition, removal, relocation, or a change of use or occupancy. Retaining walls and swimming pools also need a building permit. The Village's building permits and inspections are delivered by the RDKB Building Department.
The bylaw does not apply to a fence (other than a retaining wall), an accessory building under 10 m², a trellis, an arbour, or a wall holding soil under 1.22 m on a single-family residential parcel, or to certain factory-built homes except as the Building Code regulates them.
Steps
- Call the RDKB Building Department at 250-368-9148 before you apply to ask what your project needs.
- Fill in the application on the form the building official prescribes; the owner must sign it.
- For a simple building, include the owner's undertaking (Appendix C), a title search made within 30 days, a BC land surveyor's survey plan (the building official may waive it) and a site plan. Complex buildings need more, such as a code summary, drawings and letters of assurance from architects or engineers.
- Pay the permit fee before the permit is issued.
- Give at least 48 hours' written or online notice before starting work, and at least 48 hours' notice when you request an inspection.
Good to know
- Get a building official's written acceptance before you conceal work such as footings, framing or insulation.
- Neither the bylaw nor the Village's website says how to book an inspection or whether you can apply online. Ask the RDKB Building Department or the Village Office (250-368-8202).
- The Village's Zoning Bylaw also controls what you may build; see the zoning-lookup answer.
Official forms and pages
The same question in other places
Trail · Rossland · Montrose · Fruitvale · Castlegar · Salmo
Building permits in British Columbia: how to apply, by municipality →
Sources
- Building Bylaw No. 988, 2026, with backgrounder (PDF), Village of Warfield (read 2026-11-08)
- Permits and Licenses, Village of Warfield (read 2026-11-08)