Short answer

In Salmo you need a Village building or plumbing permit to build, renovate, add on, move or demolish a building, finish a basement, create a secondary suite, install a pool or build a retaining wall holding back more than 5 feet of soil. Apply at the Village Office or online. Work must not start until the permit is issued and paid for.

Key facts

Needed forA building or plumbing permit is needed to build a new building (including temporary and farm buildings), renovate, add on, finish a basement, move or demolish a building, change use, create a secondary suite, set up a manufactured or modular home, install a pool, or build a retaining wall holding back more than 5 feet of soil; also for plumbing and sprinkler or fire alarm systems.Building Inspections, Building Inspections page; Building Bylaw (2010), Bylaw #618, s. 6.1, 8.1 · Wording matched the official text retrieved 2026-11-08
Official wording
A Building or Plumbing Permit is required when you wish to:
construct a new building, including temporary and farm buildings
create a secondary suite
construct a retaining wall retaining more than 5 feet of soil
No person shall commence or continue any construction, alteration, reconstruction, demolition, removal, relocation or change the occupancy of any building
Not needed forThe Village lists painting; landscaping, sidewalks and driveways; fencing (fence heights are limited by the Zoning Bylaw); cabinet replacement; new roofing; and building a fireplace, installing a woodstove or chimney in an existing building. The bylaw also excludes retaining structures under 1.5 m high and uncovered decks not more than 600 mm above grade.Building Inspections, Building Inspections page; Building Bylaw (2010), Bylaw #618, s. 5.2.2, 5.2.3 · Wording matched the official text retrieved 2026-11-08
Official wording
A Permit is not required for minor non-structural changes, such as:
fencing (fence heights are limited by Village of Salmo Zoning Bylaw)
install new roofing
retaining structures less than 1.5 meters (5 ft.) in height;
decks without roofs having a difference in elevation to grade not exceeding 600 millimeters (2ft.);
How to applyApplications are available online or at the Village Office (423 Davies Avenue). Forms can be submitted in person, by email or through the Contact page. Construction must not start before the permit is issued and paid for.Building Inspections, Permit Application; Forms, Forms page · Wording matched the official text retrieved 2026-11-08
Official wording
Applications for Building Permits are available online or at the Village Office.
Construction must not commence before a building permit has been issued and paid for.
Building Permit Application
Forms can be submitted in-person, via EMAIL or by using the 'Choose files' button on the Village's CONTACT page.
What to submitA complete application form with correct contact information, signed by the owner; plans showing the designer's name and address; and the plan check deposit where required (paid at application). Complex buildings need more, including a title search and letters of assurance.Building Inspections, Permit Application; Building Bylaw (2010), Bylaw #618, s. 8.3 · Wording matched the official text retrieved 2026-11-08
Official wording
ensure that the application form is complete, contact information is correct and that the owner has signed the application
Applicant must pay plan check deposit (where required) at time of application.
All plans submitted with permit applications must bear the name and address of the designer of the building or structure.
Processing timeNot confirmed. The published pages do not say how long a permit takes.
InspectionsThe owner or contractor gives the building official 3 working days' notice (the page also says at least 72 hours). To book, call the Village office at 250-357-9433 or email appointment@salmo.ca, quoting the permit number, site address, owner's name and inspection type.Building Inspections · Wording matched the official text retrieved 2026-11-08
Official wording
It will be the responsibility of the owner/contractor to give notice of 3 working days to the building official
To book an inspection, call the Village of Salmo Office at 250-357-9433 or email us at appointment@salmo.ca.
ContactVillage office, 250-357-9433 (info@salmo.ca). The Building Inspector is at the Village Office, 423 Davies Avenue, on Wednesdays 11:00 a.m. to 12:00 p.m. Building Inspections Services line: 250-352-8155.Building Inspections, Building Inspections page · Wording matched the official text retrieved 2026-11-08
Official wording
Our Building Inspector is available in the Salmo Village Office on Wednesdays from 11:00 AM to 12:00 PM at:
For inquiries call the Building Inspections Services line at 250-352-8155.
BylawBuilding Bylaw (2010), Bylaw #618.Building Bylaw (2010), Bylaw #618, s. 1.1 · Wording matched the official text retrieved 2026-11-08
Official wording
This Bylaw may be cited for all purposes as the "Building Bylaw (2010)"

How it works

The Village of Salmo's building official reviews plans against the Building Bylaw (2010), Bylaw #618 and the BC Building Code, and inspects the work as it goes. A building or plumbing permit is needed to construct a new building (including temporary and farm buildings), renovate, add on, finish a basement, move or demolish a building, change its use, create a secondary suite, set up a manufactured or modular home, install a pool, or build a retaining wall holding back more than 5 feet of soil. It also covers plumbing, sprinkler and fire alarm systems.

The Village lists painting, landscaping, sidewalks and driveways, fencing, cabinet replacement, new roofing, and building a fireplace or installing a woodstove or chimney in an existing building as work that does not need a permit. The bylaw also excludes retaining structures under 1.5 m high and uncovered decks not more than 600 mm above grade.

Steps

  1. Get the application form online or at the Village Office (423 Davies Avenue). The form is on the Village's Forms page.
  2. Fill it in with correct contact information and sign it as owner. Include plans showing the designer's name and address. Complex buildings need more, including a title search and letters of assurance.
  3. Submit it in person, by email or through the Contact page, and pay the plan check deposit if one applies.
  4. Pay the permit fee when the permit is issued, by cheque, cash or debit card only. Do not start construction before then.
  5. Book inspections by calling 250-357-9433 or emailing appointment@salmo.ca. Give 3 working days' notice (the page also says at least 72 hours) and quote the permit number, site address, owner's name and the inspection type.

Good to know

  • The Building Inspector is at the Village Office on Wednesdays from 11:00 a.m. to 12:00 p.m. The Building Inspections Services line is 250-352-8155.
  • Under the Zoning Bylaw No. 773, an accessory building over 9.3 m² also needs a Development Permit.
  • Fewer inspections apply to farm buildings and small structures under 10 square metres.
  • The Village does not state how long a permit takes. Ask the Village Office.

Official forms and pages

The same question in other places

Fruitvale · Montrose · Castlegar · Nelson · Trail · Warfield

Building permits in British Columbia: how to apply, by municipality →

Sources

  1. Building Inspections, Village of Salmo (read 2026-11-08)
  2. Building Bylaw (2010), Bylaw #618 (PDF), Village of Salmo (read 2026-11-08)
  3. Forms, Village of Salmo (read 2026-11-08)
  4. Contact, Village of Salmo (read 2026-11-08)
  5. Zoning Bylaw No. 773, 2026 (PDF), Village of Salmo (read 2026-11-08)

Checked by script, not yet by a person: the official wording behind 7 of 8 facts was matched to the official text; 1 could not be confirmed. How answers are checked.